All 48 permitted homes are built (Q1 2026).
Also known as Taobh Chnoic.
- 9 Jun 2023Received
- 12 Jan 2024Approved
- 20 Feb 2024Final approval
- 3 Sept 2024Building started
- 16 Oct 2025Signed off
- Status
- Building started
- Decision
- Approved · 12 Jan 2024
- Size
- 48 apartments · up to 3 storeys
- Uses
- residential, apartments
- Applicant
- Cairn Homes Properties Limited
- Site
- 3.38 ha
Building progress councils’ figures, Q1 2026
- 2024Approved
- 2024Building started
- 2025First homes signed off4 sign-offs
All 48 permitted homes are built (Q1 2026).
completed · under construction · not started · 0 houses and 48 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 48 | 48 | 0 | |
| Q3 2025 | 48 | 48 | 0 | |
| Q4 2025 | 48 | 48 | 0 | |
| Q1 2026 | 48 | 0 | 48 |
The scheme
Cairn Homes Properties Limited proposes the construction of 48 duplex and apartment units in Newcastle South. The development includes the second phase of the Taobh Chnoic public park and associated infrastructure. The site is located south of Main Street and east of Athgoe Road.
it involves the construction of 48 dwellings and a public park
What the register says
Construction of 48 dwellings and open space consisting of (a) 48 duplex/apartment units in 4 three storey buildings comprising 24 two bedroom apartments and 24 three bedroom, (2-storey duplex units) all with terrace; (b) Provision of c.1.74 hectares of second phase of Taobh Chnoic public park, hard and soft landscaping (including public lighting & boundary treatment), c.1,665 sq.m of communal amenity space for duplex apartments; along with single-storey bicycle/bin stores; (c) Vehicular access will be from permitted 'Graydon' (TA06S.305343) 'Newcastle Boulevard' to the east; Provision of 73 car parking spaces and 144 bicycle spaces and all internal roads, cycleways, and paths; (d) Surface water attenuation measures, connection to water supply, and provision of foul drainage infrastructure to Irish Water specifications and all ancillary site development/construction/landscaping works on site of c.3.27 hectares, located to the south of Main Street and east of Athgoe Road and to the west of 'Graydon,' within the townland of Newcastle South
Summary from the register record.
Planning timeline 6 steps
- 9 Jun 2023Application lodged — Standard
- 12 Jan 2024Council decision — Grant
- 20 Feb 2024Final approval
- 3 Sept 2024Building started
- Q1 2026Site completed — Site completed
- 5 Apr 2029Approval runs out (estimate)
The site 3.38 ha
Boundary of Newcastle South as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 8 applications in the last 10 years
- Appeal decidedWithin the townland of, Newcastle South, Newcastle, Co. Dublin.
- WithdrawnWithin the townland of, Newcastle South, Newcastle, Co. Dublin.
- CommencedWithin the townland of Newcastle South, Newcastle, And along Athgoe Road & Hazelhatch Road (R405) to (Ground Investigations Ireland premises), Co. Dublin.
- CommencedWithin the townland of Newcastle South, Newcastle, Co. Dublin
- RefusedNewcastle, Newcastle South, Dublin 22, Dublin
- CommencedNewcastle South & Ballynakelly, Newcastle, Co. Dublin
- GrantedNewcastle South, Newcastle, Co. Dublin
- CommencedNewcastle South & Ballynakelly, Newcastle, Co. Dublin
Appeals inside the site 11 with An Coimisiún Pleanála
- Under appealNewcastle South, Newcastle, Co. Dublin
- Granted with conditionsWithin the townland of, Newcastle South, Newcastle, Co. Dublin.
- OtherNewcastle South, Newcastle, Co. Dublin.
- OtherNewcastle South, Newcastle, Co. Dublin
- OtherNewcastle South, Newcastle, Co. Dublin
- Granted with conditionsWithin the townland of Newcastle South, Newcastle and along Athgoe Road & Hazelhatch Road (R405) to Ground Investigations Ireland premises, Newcastle, Co. Dublin
- OtherWithin the townland of Newcastle South, Newcastle, Co. Dublin.
- OtherLands at Newcastle South, Phase 2, Newcastle, Co. Dublin.
- RefusedWithin townland of Newcastle South, Newcastle, Co. Dublin. (www.newcastlesouthplanning.com)
- Granted with conditionsNewcastle South and Ballynakelly, Newcastle, Co. Dublin.
- Granted with conditionsNewcastle, Co. Dublin.
Building work started inside the site 5 commencement notices
- CommencedWithin the townland of Newcastle South, Newcastle, And along Athgoe Road & Hazelhatch Road (R405) to (Ground Investigations Ireland premises), Co. Dublin.
- CommencedWithin the townland of Newcastle South, Newcastle, Co. Dublin
- CommencedWithin the townland of Newcastle South, Newcastle, Co. Dublin
- CommencedWithin the townland of Newcastle South, Newcastle, Co. Dublin
- CommencedWithin the townland of Newcastle South, Newcastle, Co. Dublin
Other big developments nearby within 2 km
- Newcastle Phase 4 · 113 homes · 3 storeys · 133 m away
- Burgage South Phase 4 · 113 homes · 3 storeys · 133 m away
- Burgage Street & Newcastle Boulevard · 50 homes · 409 m away
- Burgage Green & Newcastle Boulevard · 452 m away
- Rathcreedan Aparthotel · 156 homes · 4 storeys · 911 m away
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.