Dún Laoghaire-Rathdown County Council · DZ22A/0623 · Permission (SDZ)

Plot T 11

Cairn Homes Properties LimitedLaughanstown, Dún Laoghaire-Rathdown County Council

Approved Jan 2023; first homes signed off Nov 2023.

  1. 23 Aug 2022Received
  2. 18 Jan 2023Approved
  3. 4 Apr 2023Building started
  4. 30 Nov 2023Signed off
Status
Building started
Decision
Approved · 18 Jan 2023
Applicant
Cairn Homes Properties Limited
Site
8.54 ha

Building progress councils’ figures, Q1 2025

  1. 2023Approved
  2. 2023Building started
  3. 2023First homes signed off4 sign-offs
49
homes started on site
49
homes completed

The scheme

What the register says

This application relates to development within the Cherrywood Strategic

Summary from the register record.

Planning timeline 6 steps

  • 18 Jan 2023
    Application lodged — Standard
  • 18 Jan 2023
    Council decision — Grant permission
  • 4 Apr 2023
    Building started
  • 27 Oct 2023
    Final approval
  • Q1 2024
    Site completed — Site completed
  • 18 Jan 2028
    Approval runs out (estimate)

The site 8.54 ha

Boundary of Plot T 11 as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 61 applications in the last 10 years

Show 42 more

Showing the newest 50 of 61. The full list is in the free report.

Appeals inside the site 15 with An Coimisiún Pleanála

Building work started inside the site 5 commencement notices

Other big developments nearby within 2 km

Everything within 1 km on the map →