Dublin City Council · SHD0010/22 · SHD
Swords Road, Whitehall
472 apartmentsDublin 9, Dublin City Council
138 under construction of 472 permitted homes (Q2 2026).
Building progress councils’ figures, Q2 2026
138 under construction of 472 permitted homes (Q2 2026).
472
homes proposed
472
homes permitted
138
homes started on site
0
homes completed
completed · under construction · not started · 0 houses and 472 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 443 | 138 | 0 | |
| Q3 2025 | 443 | 138 | 0 | |
| Q4 2025 | 472 | 138 | 0 | |
| Q1 2026 | 472 | 138 | 0 | |
| Q2 2026 | 472 | 138 | 0 |
- Status
- Permitted · activity on site: yes
- Decision
- Approved · 16 Nov 2022
- Size
- 472 apartments
- Site
- 2.89 ha
- Commission case
- TA29N.313289 · Approved
The scheme
This development proposes the construction of 472 apartments and a creche at a site on Swords Road in Whitehall, Dublin 9. The project includes all associated site works.
it involves the construction of 472 residential units
Summary from the councils' pipeline record.
The site 2.89 ha
Boundary of Swords Road, Whitehall as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 3 applications in the last 10 years
Appeals inside the site 4 with An Coimisiún Pleanála
- Granted with conditionsSwords to Dublin City Centre
- Granted with conditions'Hartfield Place', Swords Road, Whitehall, Dublin 9. (www.hartfieldshd.ie)
- Refused"Hartfield Place" Swords Road, Whitehall, Dublin 9. (www.hartfieldplaceshd.com)
- Granted with conditionsWhitehall Colmcille GAA, Collins Avenue, Whitehall, Dublin 9
Building work started inside the site 7 commencement notices
- Commenced89 R132, Dublin, Dublin 9
- Commenced89 R132, Dublin, Dublin 9
- Commenced89 R132, Dublin, Dublin 9
- Commenced89 R132, Dublin
- CommencedSite at Swords Road, Whitehall, Dublin 9
- CommencedSite at Swords Road, Whitehall, Dublin 9
- CommencedSite at Swords Road, Whitehall, Dublin 9
Planning timeline 6 steps
- 12 Apr 2022Application lodged — SHD
- 16 Nov 2022Council decision — Grant
- 16 Nov 2022Commission decision — Granted
- 16 Nov 2022Final approval
- Q2 2024Building started
- 30 Dec 2027Approval runs out (estimate)
Other big developments nearby within 2 km
- Former Carmelite Convent of the Incarnation · 99 homes · 6 storeys · 651 m away
- Beaumont Road and Beaumont Drive In · 99 homes · 6 storeys · 682 m away
- Beaumont Road and Beaumont Grove Development · 99 homes · 8 storeys · 682 m away
- Collins Avenue Extension Development · 67 homes · 6 storeys · 714 m away
- 116-120 Drumcondra Road Upper · 122 homes · 5 storeys · 943 m away
- Phase 2 only (Blocks A · 50 homes · 1.0 km away
- Milner's Square Blocks B and C · 118 homes · 8 storeys · 1.0 km away
- Milner's Square · 118 homes · 8 storeys · 1.0 km away
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.