Tyrellstown Plaza Local Centre
Building: all 46 apartments are under construction (Q2 2026).
Newkey Kilmartin LtdFingal County Council
Email me when the next phase is lodged
- Status
- Building started
- Decision
- Approved · 12 Feb 2025
- Uses
- residential, apartments
- Applicant
- Newkey Kilmartin Ltd
- Site
- 4,472 m²
Building progress councils’ figures, Q2 2026
- 2025Approved
- 2025Building started
- Not yetFirst homes signed off
completed · under construction · not started · 0 houses and 46 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 46 | 0 | 0 | |
| Q3 2025 | 46 | 46 | 0 | |
| Q4 2025 | 46 | 46 | 0 | |
| Q1 2026 | 46 | 46 | 0 | |
| Q2 2026 | 46 | 46 | 0 |
Source and licence
The scheme
Newkey Kilmartin Ltd proposes the construction of two apartment buildings on lands north of Tyrellstown Plaza Local Centre and east of Bellgree. The development includes 46 residential units.
What the register says
The development proposed consists of two apartment buildings with balc…
Cut short by the council feed. Full text ↗
Summary from the register record.
Planning timeline 5 steps
- 12 Nov 2024Application lodged — Standard
- 12 Feb 2025Council decision — Grant
- 19 Mar 2025Final approval
- Q3 2025Building started
- 3 May 2030Approval runs out (estimate)
The site 4,472 m²
Boundary of Tyrellstown Plaza Local Centre as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 4 applications in the last 10 years
Appeals inside the site 2 with An Coimisiún Pleanála
Other big developments nearby within 2 km
- Hollystown · first homes signed off 2024 · 140 m away
- Hollystown-Kilmartin · first homes signed off 2024 · 580 homes · 579 m away
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.