PlanningRegister.ie
Permitted, not started · Cavan · grants of 10+ homes since 2017

Cavan planning permission: the homes nobody has started

Data updated 15 Oct 2026 · register lag up to 7 days · sources & freshness

1,580 homes in 52 sites of 10 or more have been granted permission in Cavan since 2017. A commencement notice was lodged for 57% of them. 443 still have a live permission and no start; — of those lapse within a year, and 174 have already lapsed.

1,580
homes permitted · 52 sites
57%
started · 898 homes
443
not started · live permission
—
lapse within 12 months
174
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 3

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Cavan - Belturbet2788560%240—46
Bailieborough - Cootehill1136052%121—53
Ballyjamesduff1433553%82—75

By year granted

Granted inSitesHomesStartedNot startedLapsed
2018516640%099
201939245%051
202038070%024
2021186100%0—
202269786%14—
2023517494%10—
2024622270%66—
20251029447%156—
20261336929%197—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 27 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 66% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Radar Investments Limited1660%66—
JJ McCauley Construction Limited29751%48—
Galetech Sustainable Living Limited2440%44—
Mollmac Limited25064%18—
Greyrock Trading Limited1160%16—
Erne Building Solutions Limited1140%14—
KFE Property Development Limited29888%12—
Crosserlough Construction Limited1120%12—
Shire Development Partnership1109100%0—
Drumlark Investments Limited191100%0—
Woodfort Corporate Limited186100%0—
Datum Contracts Limited1530%053
Ballyconnell Properties Limited1460%046
Latt Properties Limited136100%0—
Galrane Developments Limited125100%0—
Lyncon Properties Limited1240%024
Anney Developments Limited123100%0—
Weststate Limited120100%0—
LGS Investments Limited120100%0—
Castle Homes Ventures Limited118100%0—
Bero Construction (ROI) Limited116100%0—
Kilcarn Developments Limited116100%0—
Tully Developments Limited115100%0—
Kieran Maguire Construction114100%0—
L&M McCabe Developments Limited113100%0—
PSDC Developments Limited111100%0—
Clankee Construction and Business Development Limited110100%0—

Under appeal 1 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Lisdaran Townland 25606706523 Jul 2026Under appeal decision pendingCavan - Belturbet

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CAVAN' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 15 Oct 2026, 23:31
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.015 Oct 2026, 23:31open
An Coimisiún Pleanála case listCC BY 4.015 Oct 2026, 23:31open
Building Control Management System commencement noticesCC BY 4.015 Oct 2026, 23:31open

Recomputed weekly from the store; last built 15 Oct 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness