Cavan: homes with planning permission that nobody has started
Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness
1,580 homes in 52 sites of 10 or more have been granted permission in Cavan since 2017. A commencement notice was lodged for 54% of them. 493 still have a live permission and no start; — of those lapse within a year, and 174 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2018 | 5 | 166 | 40% | 0 | 99 |
| 2019 | 3 | 92 | 45% | 0 | 51 |
| 2020 | 3 | 80 | 70% | 0 | 24 |
| 2021 | 1 | 86 | 100% | 0 | — |
| 2022 | 6 | 97 | 86% | 14 | — |
| 2023 | 5 | 174 | 84% | 28 | — |
| 2024 | 6 | 222 | 70% | 66 | — |
| 2025 | 10 | 294 | 47% | 156 | — |
| 2026 | 13 | 369 | 20% | 229 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 73% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Radar Investments Limited | 1 | 66 | 0% | 66 | — |
| JJ McCauley Construction Limited | 2 | 97 | 51% | 48 | — |
| Galetech Sustainable Living Limited | 2 | 44 | 0% | 44 | — |
| Fitzpatrick & Heavey Homes Limited | 1 | 25 | 0% | 25 | — |
| Mollmac Limited | 2 | 50 | 64% | 18 | — |
| Castle Homes Ventures Limited | 1 | 18 | 0% | 18 | — |
| Aghateggal Services Limited | 1 | 16 | 0% | 16 | — |
| Greyrock Trading Limited | 1 | 16 | 0% | 16 | — |
| Erne Building Solutions Limited | 1 | 14 | 0% | 14 | — |
| KFE Property Development Limited | 2 | 98 | 88% | 12 | — |
| Crosserlough Construction Limited | 1 | 12 | 0% | 12 | — |
| Shire Development Partnership | 1 | 109 | 100% | 0 | — |
| Drumlark Investments Limited | 1 | 91 | 100% | 0 | — |
| Woodfort Corporate Limited | 1 | 86 | 100% | 0 | — |
| Lisdaran Developments Limited | 1 | 65 | 0% | 0 | — |
| Datum Contracts Limited | 1 | 53 | 0% | 0 | 53 |
| Ballyconnell Properties Limited | 1 | 46 | 0% | 0 | 46 |
| Latt Properties Limited | 1 | 36 | 100% | 0 | — |
| Galrane Developments Limited | 1 | 25 | 100% | 0 | — |
| Lyncon Properties Limited | 1 | 24 | 0% | 0 | 24 |
| Anney Developments Limited | 1 | 23 | 100% | 0 | — |
| LGS Investments Limited | 1 | 20 | 100% | 0 | — |
| Weststate Limited | 1 | 20 | 100% | 0 | — |
| Bero Construction (ROI) Limited | 1 | 16 | 100% | 0 | — |
| Kilcarn Developments Limited | 1 | 16 | 100% | 0 | — |
| Tully Developments Limited | 1 | 15 | 100% | 0 | — |
| Kieran Maguire Construction | 1 | 14 | 100% | 0 | — |
| L&M McCabe Developments Limited | 1 | 13 | 100% | 0 | — |
| PSDC Developments Limited | 1 | 11 | 100% | 0 | — |
| Amberwood Construction Limited | 1 | 11 | 100% | 0 | — |
Work started 25 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Billis and Drumalee Townlands 2560057 | 109 | 16 Apr 2025 | Started notice 6 Feb 2026 | |
| Drumlark Townland 2460067 | 91 | 23 Apr 2024 | Started notice 9 Dec 2024 | |
| Station Lane 23159 | 86 | 30 Nov 2023 | Started notice 15 Apr 2024 | |
| Dunaree 20407 | 86 | 16 Aug 2021 | Started notice 23 Mar 2023 | |
| Bailieborough Road 2460650 | 75 | 4 Feb 2026 | Started notice 17 Apr 2026 | |
| Cavan Road 22336 | 49 | 4 Jul 2023 | Started notice 23 Apr 2024 | |
| Latt TD 18234 | 36 | 12 Dec 2018 | Started notice 26 Oct 2020 | |
| Killyfinla 19450 | 32 | 28 Feb 2020 | Started notice 8 Jun 2023 | |
| Creighan & Burgess Acre 18528 | 25 | 9 Oct 2019 | Started notice 26 Jul 2023 | |
| Ashbrooke Housing Estate 2031 | 24 | 22 Oct 2020 | Started notice 30 Dec 2024 | |
| Magheranure 2262 | 23 | 16 Aug 2022 | Started notice 22 Apr 2024 | |
| Swellan Upper 2460265 | 20 | 16 Dec 2024 | Started notice 31 Dec 2024 | |
| Cornagleragh or Oldtown 2360337 | 20 | 9 Apr 2024 | Started notice 24 Apr 2024 | |
| 'Sliabh Rosann' 17561 | 20 | 7 Nov 2018 | Started notice 12 Dec 2022 | |
| Drumgola Wood 21390 | 18 | 8 Jul 2022 | Started notice 30 Sept 2024 | |
| Daisyhill Manor 2560212 | 16 | 5 Aug 2025 | Started notice 20 May 2026 | |
| Fairgreen Park 1934 | 16 | 29 Apr 2019 | Started notice 27 Sept 2019 | |
| Glenwood Park 2360154 | 15 | 11 Jun 2024 | Started notice 2 Jan 2025 | |
| Drumgola Wood 22261 | 15 | 13 Dec 2022 | Started notice 30 Sept 2024 | |
| Corporation Lands 21561 | 14 | 27 Jul 2022 | Started notice 22 Apr 2024 | |
| Dun Mullach 2560224 | 13 | 15 Dec 2025 | Started notice 24 Feb 2026 | |
| Kilconny 21779 | 13 | 25 Mar 2022 | Started notice 30 May 2022 | |
| Coolkill 22168 | 11 | 4 May 2023 | Started notice 30 Sept 2024 | |
| Rampart View 18292 | 11 | 28 Sept 2018 | Started notice 2 Mar 2020 | |
| Lisdrumskeagh 2460224 | 10 | 9 Dec 2024 | Started notice 19 Mar 2026 |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CAVAN' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness