Cork City: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
15,305 homes in 164 sites of 10 or more have been granted permission in Cork City since 2017. A commencement notice was lodged for 36% of them. 7,481 still have a live permission and no start; 554 of those lapse within a year, and 2,094 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 4 | 118 | 84% | 0 | 19 |
| 2018 | 22 | 1,824 | 48% | 0 | 703 |
| 2019 | 24 | 1,109 | 44% | 0 | 616 |
| 2020 | 23 | 1,126 | 51% | 0 | 555 |
| 2021 | 18 | 478 | 46% | 58 | 201 |
| 2022 | 14 | 1,193 | 37% | 749 | — |
| 2023 | 21 | 3,529 | 10% | 3,179 | — |
| 2024 | 16 | 1,314 | 71% | 384 | — |
| 2025 | 22 | 4,614 | 33% | 3,111 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Permission lapsed 41 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Tourist House 1938441 | 284 | 13 Oct 2020 | Lapsed lapsed 11 months ago | |
| (Bounded by Washington Street Woods Street 1737406 | 242 | 17 May 2018 | Lapsed lapsed 3 years ago | |
| Gillian House 1737257 | 161 | 16 Jul 2018 | Lapsed lapsed 3 years ago | |
| Carrigrohane Road 1938242 | 139 | 13 Jun 2019 | Lapsed lapsed 2 years ago | |
| St. Ann's Hill 187111 | 120 | 13 Aug 2019 | Lapsed lapsed 2 years ago | |
| Aylesbury Dvelopment 2139913 | 79 | 10 Sept 2021 | Lapsed lapsed recently | |
| Dublin Pike 176781 | 74 | 5 Jun 2018 | Lapsed lapsed 3 years ago | |
| South Main Street 1837773 | 67 | 2 Aug 2018 | Lapsed lapsed 3 years ago | |
| Heathfield 194202 | 64 | 1 May 2019 | Lapsed lapsed 2 years ago | |
| Kilnamucky 194661 | 54 | 18 Jun 2019 | Lapsed lapsed 2 years ago | |
| Riverside Farm 2039272 | 48 | 10 Feb 2021 | Lapsed lapsed 7 months ago | |
| St. Dominics 1737608 | 44 | 10 May 2018 | Lapsed lapsed 3 years ago | |
| Brocklesby St 2039048 | 42 | 17 Nov 2020 | Lapsed lapsed 10 months ago | |
| Ballinglanna 1939006 | 42 | 3 Nov 2020 | Lapsed lapsed 11 months ago | |
| Gleann Fia 1939001 | 40 | 22 Dec 2020 | Lapsed lapsed 9 months ago | |
| Reldare 195049 | 36 | 25 Nov 2019 | Lapsed lapsed 2 years ago | |
| Clarendon Brook 186245 | 36 | 12 Feb 2019 | Lapsed lapsed 3 years ago | |
| Hillfarm 195079 | 35 | 13 Nov 2019 | Lapsed lapsed 2 years ago | |
| Cope Foundation Residential 1938384 | 34 | 9 Mar 2020 | Lapsed lapsed 2 years ago | |
| Lios Cara 195325 | 31 | 4 Oct 2019 | Lapsed lapsed 2 years ago | |
| Westside 1737469 | 30 | 29 May 2018 | Lapsed lapsed 3 years ago | |
| Woodville 2039720 | 28 | 3 Aug 2021 | Lapsed lapsed 2 months ago | |
| Sarsfield Road 185275 | 27 | 22 Oct 2018 | Lapsed lapsed 3 years ago | |
| 1 Haig Gardens 1938231 | 26 | 17 Jan 2020 | Lapsed lapsed 2 years ago | |
| Glyntown 177137 | 25 | 25 Apr 2018 | Lapsed lapsed 3 years ago | |
| 95-98 Lower Glanmire Road 2039076 | 22 | 18 Nov 2020 | Lapsed lapsed 10 months ago | |
| Woodside 194557 | 22 | 14 Oct 2019 | Lapsed lapsed 2 years ago | |
| Coolymurraghue 194570 | 21 | 24 Feb 2020 | Lapsed lapsed 2 years ago | |
| Granary House 1838172 | 21 | 6 Jun 2019 | Lapsed lapsed 2 years ago | |
| Clonlara 187417 | 20 | 29 Mar 2019 | Lapsed lapsed 2 years ago | |
| Fairfield Meadows 2039568 | 19 | 31 May 2021 | Lapsed lapsed 4 months ago | |
| Moneygurney 186393 | 19 | 12 Apr 2019 | Lapsed lapsed 2 years ago | |
| No. 5 Victoria Road 1838012 | 19 | 19 Feb 2019 | Lapsed lapsed 3 years ago | |
| Ballymacthomas Street 1837914 | 19 | 10 Oct 2018 | Lapsed lapsed 3 years ago | |
| Carrigrohane Road 1737328 | 19 | 9 Nov 2017 | Lapsed lapsed 4 years ago | |
| 21 Washington Street including laneway west 1938828 | 17 | 4 Feb 2021 | Lapsed lapsed 8 months ago | |
| Dunmore Gardens 1938630 | 17 | 7 Apr 2020 | Lapsed lapsed 18 months ago | |
| Ballinglanna 2039179 | 16 | 28 Sept 2020 | Lapsed lapsed 12 months ago | |
| Off Maglin Estate 174567 | 14 | 19 Jan 2018 | Lapsed lapsed 4 years ago | |
| Unit no's. 1-3 The Courtyards 1938755 | 11 | 5 Jul 2020 | Lapsed lapsed 15 months ago | |
| 21/22 Dominic Street 2039260 | 10 | 13 Apr 2021 | Lapsed lapsed 5 months ago |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CORKCITY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness