Cork City planning permission: the homes nobody has started
Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness
10,810 homes in 78 sites of 10 or more have been granted permission in Cork City since 2021. A commencement notice was lodged for 39% of them. 6,646 still have a live permission and no start; 528 of those lapse within a year, and — have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 5
| Local electoral area | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Cork City South East | 21 | 4,038 | 32% | 2,753 | — | — |
| Cork City North West | 15 | 1,800 | 14% | 1,542 | 10 | — |
| Cork City South Central | 18 | 1,604 | 39% | 973 | 409 | — |
| Cork City South West | 10 | 1,275 | 30% | 888 | — | — |
| Cork City North East | 14 | 2,093 | 77% | 490 | 109 | — |
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2021 | 3 | 127 | 75% | 32 | — |
| 2022 | 14 | 1,193 | 58% | 496 | — |
| 2023 | 22 | 3,544 | 20% | 2,831 | — |
| 2024 | 16 | 1,314 | 72% | 370 | — |
| 2025 | 22 | 4,614 | 37% | 2,899 | — |
| 2026 | 1 | 18 | 0% | 18 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 1 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 0% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| FURADINO DEVELOPMENTS (CORK) LIMITED | 1 | 18 | 0% | 18 | — |
Work started 43 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Lahardane 2543863 | 753 | 12 Aug 2025 | Started notice 20 May 2026 | Cork City North East |
| Castletreasure 2442632 | 580 | 9 Sept 2024 | Started notice 30 Sept 2024 | Cork City South East |
| Dunkettle House 2443414 | 550 | 7 Aug 2025 | Started notice 13 Apr 2026 | Cork City North East |
| Cooneys Lane 2241226 | 253 | 29 Sept 2022 | Started notice 14 Aug 2023 | Cork City South Central |
| Site adjacent to 2140196 | 204 | 23 Aug 2022 | Started notice 29 Jun 2026 | Cork City South East |
| located adjacent to Telus International 2443351 | 196 | 5 Mar 2025 | Started notice 29 Jun 2026 | Cork City South East |
| Off Maglin Road 2342446 | 162 | 19 Aug 2024 | Started notice 23 Dec 2024 | Cork City South West |
| Ballycureen 2140353 | 134 | 18 Jul 2023 | Started notice 4 Nov 2026 | Cork City South Central |
| Richmond 2342154 | 130 | 17 Oct 2023 | Started notice 20 Mar 2024 | Cork City North East |
| Carriganarra 2241644 | 99 | 29 Jan 2024 | Started notice 10 Apr 2024 | Cork City South West |
| Dublin Pike and Ballyhooly Road 2140038 | 96 | 9 Feb 2023 | Started notice 27 Nov 2023 | Cork City North East |
| South Douglas Road 2442645 | 93 | 19 May 2025 | Started notice 27 Jan 2026 | Cork City South Central |
| Lands between Kennedy Quay 2140702 | 84 | 30 May 2023 | Started notice 11 Nov 2026 | Cork City South East |
| Aylesbury Dvelopment 2139913 | 79 | 10 Sept 2021 | Started notice 29 Oct 2021 | Cork City South East |
| Kilronan 2140189 | 60 | 23 May 2023 | Started notice 19 Aug 2024 | Cork City North West |
| Classes 2140222 | 58 | 22 Feb 2022 | Started notice 22 Feb 2023 | Cork City South West |
| Fairfield Meadows 2140732 | 46 | 19 May 2022 | Started notice 30 Dec 2022 | Cork City North West |
| former part 1 storey 2241247 | 43 | 20 Apr 2023 | Started notice 27 Sept 2024 | Cork City North West |
| Cooneys Lane 2543686 | 42 | 3 Jun 2025 | Started notice 29 Sept 2026 | Cork City South Central |
| Coolymurraghue 2240976 | 41 | 21 Sept 2023 | Started notice 17 May 2024 | Cork City North West |
| Formers Lakelands Tavern 2139911 | 39 | 11 Aug 2022 | Started notice 10 Apr 2024 | Cork City South East |
| Ballinglanna 2140507 | 30 | 7 Jun 2022 | Started notice 11 Apr 2023 | Cork City North East |
| Ballybrack 2140405 | 29 | 15 Nov 2023 | Started notice 11 Aug 2025 | Cork City South East |
| Old Market Place 2140384 | 27 | 9 Aug 2023 | Started notice 24 Sept 2024 | Cork City North West |
| Woodside 2443381 | 26 | 20 Aug 2025 | Started notice 23 Mar 2026 | Cork City North West |
| Lower Friars Walk 2140066 | 26 | 15 May 2023 | Started notice 25 Sept 2024 | Cork City South Central |
| Ballinvriskig 2140600 | 24 | 7 Apr 2022 | Started notice 27 Sept 2024 | Cork City North East |
| Ard Na Gaoithe 2342337 | 21 | 22 Apr 2024 | Started notice 27 Dec 2024 | Cork City South Central |
| Garranedarragh 2443524 | 20 | 1 Sept 2025 | Started notice 24 Aug 2026 | Cork City South West |
| Glenmount Crest 2241480 | 20 | 29 Apr 2024 | Started notice 25 Mar 2025 | Cork City North East |
| Rochestown Road 2443350 | 19 | 22 Jul 2025 | Started notice 11 Nov 2025 | Cork City South East |
| 67-69 South Mall 2342233 | 17 | 22 Jul 2024 | Started notice 13 May 2025 | Cork City South Central |
| Site fronting onto Dunbar Street 2443491 | 16 | 13 Oct 2025 | Started notice 8 Apr 2026 | Cork City South Central |
| Grange Road 2442997 | 16 | 18 Nov 2024 | Started notice 25 Sept 2025 | Cork City South East |
| Merton Lodge 2241080 | 16 | 22 Mar 2023 | Started notice 30 Oct 2023 | Cork City South West |
| Old Fort Gate 2140554 | 16 | 28 Apr 2022 | Started notice 24 Apr 2024 | Cork City South West |
| Baker Street 2139822 | 16 | 2 Dec 2021 | Started notice 10 Jun 2022 | Cork City South West |
| Ivy Lawn 2342205 | 15 | 11 Mar 2024 | Started notice 23 Dec 2024 | Cork City South Central |
| 95 Gerald Griffin Street 2241532 | 15 | 7 Sept 2023 | Started notice 15 Oct 2024 | Cork City North West |
| Kennedy Quay 2442613 | 14 | 17 Jun 2024 | Started notice 30 Sept 2024 | Cork City South East |
| Carmelite Place 2140598 | 14 | 23 May 2022 | Started notice 16 Sept 2024 | Cork City South Central |
| 8&8A Ballinure Cottages 2140402 | 13 | 19 Jan 2022 | Started notice 2 Aug 2024 | Cork City South East |
| Hettyfield 2139825 | 12 | 17 May 2023 | Started notice 12 Sept 2023 | Cork City South East |
How it is counted
- A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CORKCITY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| An Coimisiún Pleanála case list | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| Building Control Management System commencement notices | CC BY 4.0 | 6 Nov 2026, 23:00 | open |