Cork City: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
15,305 homes in 164 sites of 10 or more have been granted permission in Cork City since 2017. A commencement notice was lodged for 36% of them. 7,481 still have a live permission and no start; 554 of those lapse within a year, and 2,094 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 4 | 118 | 84% | 0 | 19 |
| 2018 | 22 | 1,824 | 48% | 0 | 703 |
| 2019 | 24 | 1,109 | 44% | 0 | 616 |
| 2020 | 23 | 1,126 | 51% | 0 | 555 |
| 2021 | 18 | 478 | 46% | 58 | 201 |
| 2022 | 14 | 1,193 | 37% | 749 | — |
| 2023 | 21 | 3,529 | 10% | 3,179 | — |
| 2024 | 16 | 1,314 | 71% | 384 | — |
| 2025 | 22 | 4,614 | 33% | 3,111 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Permission, no start 36 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Centre Park Road 2342106 | 1,325 | 5 Oct 2023 | Not started lapses in 7 years | |
| Convent Avenue 2543847 | 957 | 6 Nov 2025 | Not started lapses in 9 years | |
| Jacobs Island 2342275 | 441 | 7 Dec 2023 | Not started lapses in 2 years | |
| Jacobs Island 2341994 | 441 | 21 Aug 2023 | Not started lapses in 2 years | |
| adjoining ESB Networks DAC 2543819 | 348 | 29 Sept 2025 | Not started lapses in 6 years | |
| St Josephs Convent 2443455 | 335 | 9 Jun 2025 | Not started lapses in 4 years | |
| Horgans Quay 2443545 | 302 | 1 Apr 2025 | Not started lapses in 4 years | |
| Saint Kevins Hospital 2442796 | 265 | 1 Jul 2024 | Not started lapses in 3 years | |
| Cooneys Lane 2241540 | 254 | 21 Feb 2023 | Not started lapses within a year | |
| Cooneys Lane 2241226 | 253 | 29 Sept 2022 | Not started lapses within a year | |
| Ringwood 2443031 | 246 | 6 May 2025 | Not started lapses in 4 years | |
| No. 9 2442982 | 220 | 17 Oct 2025 | Not started lapses in 4 years | |
| Rossa Avenue 2241677 | 205 | 6 Jul 2023 | Not started lapses in 2 years | |
| located adjacent to Telus International 2443351 | 196 | 5 Mar 2025 | Not started lapses in 3 years | |
| Fronting onto Centre Park Road 2443472 | 176 | 19 Mar 2025 | Not started lapses in 3 years | |
| Ballycureen 2140353 | 134 | 18 Jul 2023 | Not started lapses in 2 years | |
| Richmond 2342154 | 130 | 17 Oct 2023 | Not started lapses in 2 years | |
| Barrys Field 2543605 | 124 | 30 Sept 2025 | Not started lapses in 4 years | |
| Clarkes Hill 2140135 | 100 | 6 Jun 2023 | Not started lapses in 2 years | |
| Villa Maria 2342092 | 90 | 6 May 2025 | Not started lapses in 4 years | |
| Lands between Kennedy Quay 2140702 | 84 | 30 May 2023 | Not started lapses in 7 years | |
| Lands associated with 2342162 | 44 | 22 Jan 2025 | Not started lapses in 3 years | |
| Cooneys Lane 2342246 | 37 | 27 Nov 2023 | Not started lapses in 2 years | |
| 21-24 Leitrim Street 2342265 | 21 | 24 Sept 2024 | Not started lapses in 3 years | |
| South Douglas Road 2442647 | 20 | 19 May 2025 | Not started lapses in 4 years | |
| Ballinvriskig 2140745 | 20 | 6 Sept 2024 | Not started lapses in 3 years | |
| Site Between 81 & 82 2342206 | 19 | 21 Oct 2025 | Not started lapses in 4 years | |
| Glenmont Crest 2342142 | 19 | 29 Jan 2024 | Not started lapses in 2 years | |
| 95 Gerald Griffin Street 2442998 | 18 | 14 Jul 2025 | Not started lapses in 4 years | |
| 40-41 Popes Quay 2342562 | 18 | 9 Dec 2024 | Not started lapses in 3 years | |
| Farranree Sheltered Housing Association CLG 2241592 | 18 | 11 May 2023 | Not started lapses in 2 years | |
| Site fronting onto Dunbar Street 2443491 | 16 | 13 Oct 2025 | Not started lapses in 4 years | |
| 29 Coach Street 2342429 | 15 | 26 Aug 2024 | Not started lapses in 3 years | |
| Kennedy Quay 2442613 | 14 | 17 Jun 2024 | Not started lapses in 3 years | |
| Rochestown Inn 2342294 | 12 | 8 Jul 2024 | Not started lapses in 3 years | |
| Watercourse Road 2241463 | 10 | 7 Dec 2023 | Not started lapses in 2 years |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CORKCITY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness