Dún Laoghaire-Rathdown: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
23,991 homes in 161 sites of 10 or more have been granted permission in Dún Laoghaire-Rathdown since 2017. A commencement notice was lodged for 63% of them. 7,056 still have a live permission and no start; 1,150 of those lapse within a year, and 991 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 7
| Local electoral area | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Glencullen-Sandyford | 42 | 6,723 | 62% | 2,101 | 149 | 195 |
| Killiney-Shankill | 35 | 6,127 | 76% | 1,296 | — | 198 |
| Dundrum | 14 | 2,983 | 59% | 1,211 | 125 | — |
| Stillorgan | 28 | 3,539 | 59% | 930 | 577 | 300 |
| Bray East | 1 | 586 | 0% | 586 | — | — |
| Dún Laoghaire | 26 | 2,427 | 62% | 567 | 299 | 298 |
| Blackrock | 15 | 1,606 | 62% | 365 | — | — |
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 8 | 382 | 79% | 0 | 82 |
| 2018 | 15 | 3,794 | 99% | 0 | 19 |
| 2019 | 25 | 2,638 | 86% | 0 | 361 |
| 2020 | 17 | 3,102 | 90% | 0 | 298 |
| 2021 | 10 | 2,685 | 66% | 669 | 231 |
| 2022 | 10 | 1,863 | 50% | 926 | — |
| 2023 | 13 | 1,346 | 36% | 862 | — |
| 2024 | 19 | 2,024 | 46% | 1,097 | — |
| 2025 | 29 | 4,617 | 38% | 2,613 | — |
| 2026 | 15 | 1,540 | 9% | 889 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 29 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 36% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Shankill Property Investments Limited | 1 | 586 | 0% | 586 | — |
| Homeland Silverpines Limited | 1 | 463 | 0% | 463 | — |
| Ironborn Real Estate Limited | 1 | 438 | 0% | 438 | — |
| Clonkeen Investments DAC | 1 | 299 | 0% | 299 | — |
| Atlas GP Limited | 1 | 255 | 0% | 255 | — |
| Palemink Limited | 1 | 190 | 0% | 190 | — |
| Pembroke Partnership Limited | 1 | 115 | 0% | 115 | — |
| Bridgeclip (Developments) Limited | 1 | 112 | 0% | 112 | — |
| KW PRS ICAV | 2 | 389 | 74% | 102 | — |
| Aeval Unlimited Company | 1 | 685 | 100% | 0 | — |
| Cairns Homes Properties Limited | 1 | 576 | 100% | 0 | — |
| Sandyford GP Limited | 1 | 564 | 100% | 0 | — |
| 1 Wyckham Land Limited | 1 | 531 | 100% | 0 | — |
| Cairn Homes Properties Limited | 1 | 377 | 100% | 0 | — |
| Cosgrave Developments | 1 | 368 | 100% | 0 | — |
| Lulani Dalguise Limited | 1 | 298 | 0% | 0 | 298 |
| Baker Forge Properties Limited | 1 | 276 | 100% | 0 | — |
| Murphystown Land Developments DAC | 1 | 249 | 100% | 0 | — |
| Castdale Limited | 1 | 243 | 100% | 0 | — |
| KW Investment Funds ICAV | 1 | 232 | 100% | 0 | — |
| Winterbrook Homes Limited | 1 | 231 | 0% | 0 | 231 |
| Strand Court Limited | 1 | 210 | 100% | 0 | — |
| Adroit Operations Limited | 1 | 203 | 100% | 0 | — |
| Ketut Limited | 1 | 200 | 100% | 0 | — |
| Granville Hall Partnership | 1 | 142 | 100% | 0 | — |
| Dundrum Retail GP DAC | 1 | 107 | 100% | 0 | — |
| Crekav Trading GP Limited | 1 | 102 | 100% | 0 | — |
| B&C Contractors Managhan Limited | 1 | 67 | 100% | 0 | — |
| Walled Orchard GP3 Limited | 1 | 26 | 100% | 0 | — |
Permission lapsed 10 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Dalguise House . Monkstown Road ABP-306949 | 298 | 25 Aug 2020 | Lapsed lapsed 13 months ago | Monkstown |
| Mount Saint Mary's and Saint Joseph's ABP-310138 | 231 | 25 Aug 2021 | Lapsed lapsed recently | Stillorgan |
| Laughanstown ABP30342919 | 184 | 18 Apr 2019 | Lapsed lapsed 2 years ago | Killiney-Shankill |
| Beacon South Quarter mixed use scheme D18A/0785 | 84 | 17 Jun 2019 | Lapsed lapsed 2 years ago | Glencullen-Sandyford |
| Clay Farm D17A/0468 | 69 | 24 Aug 2017 | Lapsed lapsed 4 years ago | Ballyogan |
| Overall site of c.1.14ha at Weavers Hall D17A/0486 | 50 | 7 Mar 2019 | Lapsed lapsed 3 years ago | Foxrock |
| 62 & 63 (Innisfree), Stepaside Lane D18A/0971 | 29 | 10 Oct 2019 | Lapsed lapsed 2 years ago | Stepaside |
| Killart D18A/0402 | 19 | 26 Jul 2018 | Lapsed lapsed 16 months ago | Monaloe Corner |
| Mount Auburn D19A/0054 | 14 | 29 Aug 2019 | Lapsed lapsed 2 years ago | Killiney-Shankill |
| Stepaside Park D16A/0650 | 13 | 20 Apr 2017 | Lapsed lapsed 4 years ago | Stepaside |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'DLR' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness