Donegal: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

3,172 homes in 96 sites of 10 or more have been granted permission in Donegal since 2017. A commencement notice was lodged for 45% of them. 1,556 still have a live permission and no start; 59 of those lapse within a year, and 159 have already lapsed.

3,172
homes permitted · 96 sites
45%
started · 1,413 homes
1,556
not started · live permission
59
lapse within 12 months
159
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
20172680%068
201847438%046
2019835982%3033
2020940366%12712
20214119100%0
2022616965%59
2023718066%62
20241435750%178
20251946751%218
2026239766%882

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 75% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
CR RENAISSANCE PROPERTIES Limited427020%215
MCHENRY ASSET HOLDINGS LIMITED1940%94
PROPERTY HOLD Limited420359%84
PJD CONSTRUCTION LONDON Limited2760%76
GEORGE DOHERTY CONSTRUCTION (IRL) Limited430962%5858
WARREN KEARNS OF W.P. KEARNS Limited2450%45
HANNAFORD PROJECT MANAGEMENT (IRELAND) LIMITED1430%43
LETTERKENNY ROSEMOUNT HOMES LIMITED1420%42
MC HUGH BROS. BUILDERS Limited2390%39
LEXUS PROJECTS LIMITED2380%38
NEWTOWNSTEWART CONSTRUCTION LIMITED1350%35
ROARTY DEVELOPMENTS Limited1340%34
AUGHRIM HEIGHTS DEVELOPMENT COMPANY LIMITED1330%33
AXIS CONSTRUCTION LIMITED24328%31
CILLANOIR DEVELOPMENTS LIMITED27864%28
GERALD MCCALLION ON BEHALF OF GLENTURAS CONSTRUCTION Limited1280%28
DORRIAN CONSTRUCTION LIMITED1240%24
MEADOWFIELD DEVELOPMENTS Limited1240%24
TOPM DEVELOPMENTS Limited1220%22
R.I. SCOTT CONSTRUCTION LIMITED1200%20
NIALL DEVINE OF N&R DEVINE (IRL) Limited1190%19
BREEZY POINT CAPITAL Limited1150%15
DANIELLE MCCAULEY DMR DEVELOPMENTS1140%14
LEMACROSSAN INVESTMENTS Limited1130%13
C & C PROPERTY INVESTMENT Limited1120%12
BRADLEY & DOHERTY PROPERTIES LIMITED1120%12
SOUTH DERRY REPRODUCTION (ROI) LIMITED1100%10
TWIN ESTATES LONDON LIMITED1100%10
CARNVALLEY HOLDINGS Limited2121100%0
SAYVALE 26 Limited162100%0

Permission lapsed 6 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
CREEVESMITH 17500665813 Apr 2017Lapsed lapsed 4 years ago
CONVOY TOWNPARKS 19512963320 Nov 2019Lapsed lapsed 2 years ago
CARNAMUGGAGH LOWER 18511733017 Oct 2018Lapsed lapsed 5 years ago
ELEVEN BALLYBOES 1851073163 Oct 2018Lapsed lapsed 3 years ago
FINTRA ROAD 19511101217 Jun 2020Lapsed lapsed 15 months ago
KILL 1750732108 Nov 2017Lapsed lapsed 4 years ago

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'DONEGAL' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.