Galway City: homes with planning permission that nobody has started
Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness
3,094 homes in 64 sites of 10 or more have been granted permission in Galway City since 2017. A commencement notice was lodged for 36% of them. 1,034 still have a live permission and no start; 126 of those lapse within a year, and 831 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 2 | 126 | 70% | 0 | 38 |
| 2018 | 6 | 487 | 0% | 30 | 457 |
| 2019 | 9 | 421 | 38% | 0 | 262 |
| 2020 | 7 | 334 | 100% | 0 | — |
| 2021 | 4 | 125 | 0% | 51 | 74 |
| 2022 | 5 | 191 | 38% | 118 | — |
| 2023 | 4 | 387 | 7% | 358 | — |
| 2024 | 9 | 211 | 69% | 65 | — |
| 2025 | 7 | 432 | 50% | 218 | — |
| 2026 | 11 | 380 | 20% | 194 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 74% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Cleverson Limited | 1 | 272 | 0% | 272 | — |
| Lock House Developments Limited | 1 | 168 | 0% | 168 | — |
| Cairn Homes Properties Limited | 1 | 89 | 0% | 89 | — |
| Sean Talamh Development Limited | 1 | 86 | 0% | 86 | — |
| Weaveridge Limited | 1 | 75 | 0% | 75 | — |
| Damree Developments Limited | 1 | 47 | 0% | 47 | — |
| Highcross Developments Limited | 1 | 40 | 0% | 40 | — |
| Catena Property Company Limited | 1 | 39 | 0% | 39 | — |
| Renaissance Property Limited | 2 | 61 | 61% | 24 | — |
| O'Malley Construction Company Limited | 1 | 18 | 0% | 18 | — |
| Burkeway Homes Limited | 2 | 42 | 69% | 13 | — |
| Abbeyclare Construction Limited | 1 | 12 | 0% | 12 | — |
| NTM ROI Seed Capital LP | 1 | 394 | 0% | 0 | 394 |
| Evolution Asset Holdings Limited | 1 | 133 | 0% | 0 | 133 |
| Ardstone Homes | 1 | 88 | 100% | 0 | — |
| Bomac Developments Limited | 2 | 80 | 100% | 0 | — |
| K King Construction | 1 | 64 | 0% | 0 | 64 |
| Centento Limited | 1 | 64 | 100% | 0 | — |
| K King Construction Claregalway Limited | 2 | 59 | 100% | 0 | — |
| JLH Property Holding Company | 1 | 53 | 0% | 0 | 53 |
| Leadlane (Mincloon) Limited | 1 | 48 | 0% | 0 | — |
| Goaley Crescent Contracts Limited | 2 | 41 | 100% | 0 | — |
| Foxfield Inns DAC | 1 | 38 | 0% | 0 | 38 |
| Quadrant Investment Unlimited Company | 2 | 37 | 100% | 0 | — |
| K King Construction Limited | 1 | 35 | 0% | 0 | 35 |
| Westlyn Property Limited | 1 | 26 | 100% | 0 | — |
| Graphite Fusion Limited | 1 | 24 | 0% | 0 | — |
| Aosóg Centre Company Limited by Guarantee | 1 | 18 | 100% | 0 | — |
| Exeter Ireland Property iii Limited | 1 | 16 | 0% | 0 | 16 |
| Leadlane (Clybaun) Limited | 1 | 15 | 100% | 0 | — |
Under appeal 5 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Mincloon 2560375 | 48 | 31 Jul 2026 | Under appeal decision pending | |
| Renmore 2560322 | 24 | 12 May 2026 | Under appeal decision pending | |
| 206 Upper Salthill Road 2560381 | 14 | 29 May 2026 | Under appeal decision pending | |
| Rahoon 2560320 | 13 | 9 Apr 2026 | Under appeal decision pending | |
| Rahoon Road Mincloon 2560335 | 12 | 28 May 2026 | Under appeal decision pending |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'GALWAYCITY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.