PlanningRegister.ie
Permitted, not started · Galway City · grants of 10+ homes since 2017

Galway City: homes with planning permission that nobody has started

Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness

3,094 homes in 64 sites of 10 or more have been granted permission in Galway City since 2017. A commencement notice was lodged for 36% of them. 1,034 still have a live permission and no start; 126 of those lapse within a year, and 831 have already lapsed.

3,094
homes permitted · 64 sites
36%
started · 1,118 homes
1,034
not started · live permission
126
lapse within 12 months
831
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
2017212670%038
201864870%30457
2019942138%0262
20207334100%0—
202141250%5174
2022519138%118—
202343877%358—
2024921169%65—
2025743250%218—
20261138020%194—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 74% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Cleverson Limited12720%272—
Lock House Developments Limited11680%168—
Cairn Homes Properties Limited1890%89—
Sean Talamh Development Limited1860%86—
Weaveridge Limited1750%75—
Damree Developments Limited1470%47—
Highcross Developments Limited1400%40—
Catena Property Company Limited1390%39—
Renaissance Property Limited26161%24—
O'Malley Construction Company Limited1180%18—
Burkeway Homes Limited24269%13—
Abbeyclare Construction Limited1120%12—
NTM ROI Seed Capital LP13940%0394
Evolution Asset Holdings Limited11330%0133
Ardstone Homes188100%0—
Bomac Developments Limited280100%0—
K King Construction1640%064
Centento Limited164100%0—
K King Construction Claregalway Limited259100%0—
JLH Property Holding Company1530%053
Leadlane (Mincloon) Limited1480%0—
Goaley Crescent Contracts Limited241100%0—
Foxfield Inns DAC1380%038
Quadrant Investment Unlimited Company237100%0—
K King Construction Limited1350%035
Westlyn Property Limited126100%0—
Graphite Fusion Limited1240%0—
Aosóg Centre Company Limited by Guarantee118100%0—
Exeter Ireland Property iii Limited1160%016
Leadlane (Clybaun) Limited115100%0—

Under appeal 5 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Mincloon 25603754831 Jul 2026Under appeal decision pending
Renmore 25603222412 May 2026Under appeal decision pending
206 Upper Salthill Road 25603811429 May 2026Under appeal decision pending
Rahoon 2560320139 Apr 2026Under appeal decision pending
Rahoon Road Mincloon 25603351228 May 2026Under appeal decision pending

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'GALWAYCITY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.026 Sept 2026, 07:08open
An Coimisiún Pleanála case listCC-BY-4.026 Sept 2026, 07:08open
Building Control Management System commencement noticesCC-BY-4.026 Sept 2026, 07:08open

Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness