Galway City planning permission: the homes nobody has started

Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness

1,866 homes in 41 sites of 10 or more have been granted permission in Galway City since 2021. A commencement notice was lodged for 30% of them. 973 still have a live permission and no start; — of those lapse within a year, and 49 have already lapsed.

1,866
homes permitted · 41 sites
30%
started · 566 homes
973
not started · live permission
—
lapse within 12 months
49
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 3

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Galway City Central1571135%404—10
Galway City East948118%372——
Galway City West1767434%197—39

By year granted

Granted inSitesHomesStartedNot startedLapsed
20212490%049
2022411663%43—
2023540311%358—
2024921175%52—
2025743250%218—
20261465511%302—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 20 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 57% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Cleverson Limited12720%272—
Lock House Developments Limited11680%168—
Cairn Homes Properties Limited1890%89—
Sean Talamh Development Limited1860%86—
Renaissance Property Limited1240%24—
O'Malley Construction Company Limited1180%18—
Bomac Developments Limited280100%0—
Leadlane (Mincloon) Limited1480%0—
Goaley Crescent Contracts Limited241100%0—
Catena Property Company Limited1390%039
Quadrant Investment Unlimited Company237100%0—
K King Construction Claregalway Limited132100%0—
Westlyn Property Limited126100%0—
Graphite Fusion Limited1240%0—
Sweetbay Limited116100%0—
The Crescent Company Ownership115100%0—
Leadlane (Clybaun) Limited115100%0—
Canfeen Investments Limited1140%0—
Burkeway Homes Limited113100%0—
Leadlane (Cappagh) Limited112100%0—

Permission lapsed 2 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
105 Salthill Road Upper 211973928 Oct 2021Lapsed lapsed recentlyGalway City West
111 Upper Newcastle Road 211461010 Aug 2021Lapsed lapsed 3 months agoGalway City Central

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'GALWAYCITY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.06 Nov 2026, 23:00open
An Coimisiún Pleanála case listCC BY 4.06 Nov 2026, 23:00open
Building Control Management System commencement noticesCC BY 4.06 Nov 2026, 23:00open