Galway City planning permission: the homes nobody has started

Data updated 15 Oct 2026 · register lag up to 7 days · sources & freshness

3,529 homes in 71 sites of 10 or more have been granted permission in Galway City since 2017. A commencement notice was lodged for 41% of them. 1,262 still have a live permission and no start; 126 of those lapse within a year, and 675 have already lapsed.

3,529
homes permitted · 71 sites
41%
started · 1,447 homes
1,262
not started · live permission
126
lapse within 12 months
675
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 3

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Galway City East2092329%45987169
Galway City Central241,51542%434—404
Galway City West271,09150%36939102

By year granted

Granted inSitesHomesStartedNot startedLapsed
2017212670%038
201864878%30417
20191153373%0146
20208366100%0—
202141250%5174
2022519138%118—
2023540311%358—
2024921175%52—
2025743250%218—
20261465511%435—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 62% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Cleverson Limited12720%272—
Lock House Developments Limited11680%168—
Cairn Homes Properties Limited1890%89—
Sean Talamh Development Limited1860%86—
Weaveridge Limited1750%75—
Catena Property Company Limited1390%39—
Renaissance Property Limited39876%24—
O'Malley Construction Company Limited1180%18—
NTM ROI Seed Capital LP13940%0394
Evolution Asset Holdings Limited11330%0133
Ardstone Homes188100%0—
Bomac Developments Limited280100%0—
Centento Limited164100%0—
K King Construction1640%064
K King Construction Claregalway Limited259100%0—
JLH Property Holding Company153100%0—
Leadlane (Mincloon) Limited1480%0—
Burkeway Homes Limited242100%0—
Goaley Crescent Contracts Limited241100%0—
Foxfield Inns DAC1380%038
Quadrant Investment Unlimited Company237100%0—
K King Construction Limited135100%0—
Westlyn Property Limited126100%0—
Graphite Fusion Limited1240%0—
Aosóg Centre Company Limited by Guarantee118100%0—
Sweetbay Limited116100%0—
Leadlane (Clybaun) Limited115100%0—
Dacks Developments115100%0—
The Crescent Company Ownership115100%0—
Cahermorris Development Limited115100%0—

Lapses within a year 3 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Briarhill Shopping Centre 203427514 Feb 2022Lapsing lapses in 4 monthsGalway City East
105 Salthill Road Upper 211973928 Oct 2021Lapsing lapses within a monthGalway City West
Estelle 201781211 Feb 2021Lapsing lapses in 11 monthsGalway City East

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'GALWAYCITY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 15 Oct 2026, 23:31
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.015 Oct 2026, 23:31open
An Coimisiún Pleanála case listCC BY 4.015 Oct 2026, 23:31open
Building Control Management System commencement noticesCC BY 4.015 Oct 2026, 23:31open

Recomputed weekly from the store; last built 15 Oct 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.