Kildare planning permission: the homes nobody has started
Data updated 20 Nov 2026 · register lag up to 7 days · sources & freshness
7,771 homes in 130 sites of 10 or more have been granted permission in Kildare since 2021. A commencement notice was lodged for 48% of them. 3,181 still have a live permission and no start; 881 of those lapse within a year, and 292 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 8
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2021 | 7 | 462 | 41% | 0 | 272 |
| 2022 | 20 | 1,237 | 24% | 921 | 10 |
| 2023 | 16 | 720 | 71% | 197 | 10 |
| 2024 | 33 | 1,834 | 94% | 104 | — |
| 2025 | 33 | 1,557 | 47% | 799 | — |
| 2026 | 21 | 1,961 | 15% | 1,160 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 49% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Briargate Developments Newbridge Limited | 2 | 329 | 0% | 329 | — |
| The Land Development Agency | 1 | 219 | 0% | 219 | — |
| Lagan Homes South Salt Limited | 1 | 164 | 0% | 164 | — |
| Alchemy Homes Development (Kilcullen) Limited | 1 | 125 | 0% | 125 | — |
| Ladas Property Company Limited | 1 | 115 | 0% | 115 | — |
| Eurkon (Kildare) Limited | 1 | 88 | 0% | 88 | — |
| Seattle Construction Limited | 1 | 76 | 0% | 76 | — |
| David Walsh Homes Limited | 1 | 74 | 0% | 74 | — |
| Killross Properties Limited | 3 | 77 | 13% | 67 | — |
| Kilcullenbridge Developments Limited | 1 | 67 | 0% | 67 | — |
| Tapeford Limited | 1 | 58 | 0% | 58 | — |
| Balyna Hotel Limited | 1 | 54 | 0% | 54 | — |
| Debussy Properties Limited | 2 | 164 | 70% | 50 | — |
| Nua Healthcare Services Limited | 1 | 50 | 0% | 50 | — |
| Kestorra Limited | 2 | 47 | 45% | 26 | — |
| O’Flynn Construction (Dublin) Limited | 1 | 25 | 0% | 25 | — |
| Clonmel Enterprises Limited | 1 | 16 | 0% | 16 | — |
| Andrews Construction Limited | 1 | 14 | 0% | 14 | — |
| MA Tudor Investments Limited | 1 | 14 | 0% | 14 | — |
| Ascot Construction Limited | 1 | 12 | 0% | 12 | — |
| Elmendorf Limited | 1 | 11 | 0% | 11 | — |
| Resource Five Limited | 1 | 10 | 0% | 10 | — |
| Cairn Homes Properties Limited | 2 | 380 | 100% | 0 | — |
| Westar Homes Limited | 2 | 291 | 100% | 0 | — |
| Ballymore Land Limited | 3 | 187 | 100% | 0 | — |
| Randelswood Holdings Limited | 1 | 172 | 100% | 0 | — |
| Cairn Homes | 1 | 148 | 0% | 0 | 148 |
| Columbia Estates Management (IE) Limited | 1 | 136 | 100% | 0 | — |
| Bettystown Developments Limited | 2 | 129 | 100% | 0 | — |
| Glan Developments | 1 | 98 | 0% | 0 | 98 |
Lapses within a year 6 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Ballymany 22312704 | 309 | 6 Sept 2022 | Lapsing lapses in 10 months | Newbridge |
| Devoy Barracks 22313276 | 219 | 13 Oct 2022 | Lapsing lapses in 11 months | Naas |
| Earl's Court 22690 | 164 | 5 Oct 2022 | Lapsing lapses in 11 months | Naas |
| Riverside 22312861 | 125 | 25 Aug 2022 | Lapsing lapses in 9 months | Berney's Inch |
| Station Road 211113 | 52 | 23 Mar 2022 | Lapsing lapses in 4 months | Byrnes Crossroads |
| Westbank House 211340 | 12 | 29 Mar 2022 | Lapsing lapses in 4 months | Newbridge |
How it is counted
- A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KILDARE' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 20 Nov 2026, 23:03
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC BY 4.0 | 20 Nov 2026, 23:03 | open |
| An Coimisiún Pleanála case list | CC BY 4.0 | 20 Nov 2026, 23:03 | open |
| Building Control Management System commencement notices | CC BY 4.0 | 20 Nov 2026, 23:03 | open |
Recomputed weekly from the store; last built 20 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness