Permitted, not started · Kildare · grants of 10+ homes since 2017

Kildare: homes with planning permission that nobody has started

Data updated 3 Oct 2026 · register lag up to 7 days · sources & freshness

14,796 homes in 251 sites of 10 or more have been granted permission in Kildare since 2017. A commencement notice was lodged for 42% of them. 4,588 still have a live permission and no start; 929 of those lapse within a year, and 3,625 have already lapsed.

14,796
homes permitted · 251 sites
42%
started · 6,178 homes
4,588
not started · live permission
929
lapse within 12 months
3,625
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 4

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Maynooth343,06035%1,244148694
Naas473,00541%830175947
Leixlip151,43644%254—551
Celbridge1590333%170—437

By year granted

Granted inSitesHomesStartedNot startedLapsed
2017824242%0140
2018282,05443%01,162
2019341,77544%268724
2020402,66548%01,383
2021211,16329%294196
2022211,32329%93210
20231773547%38110
2024311,58175%400—
2025321,54342%870—
2026191,71513%1,443—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 51% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Briargate Developments Newbridge Limited23290%329—
Ardstone Homes Limited35612%268283
Cairn Homes Properties Limited466321%243283
The Land Development Agency12190%219—
Lagan Homes South Salt Limited11640%164—
Cairn Homes11480%148—
Pousterle Limited11360%136—
Alchemy Homes Development (Kilcullen) Limited11250%125—
Ladas Property Company Limited11150%115—
Glan Developments1980%98—
Eurkon (Kildare) Limited1880%88—
Thoval Properties Limited1870%87—
Seattle Construction Limited1760%76—
David Walsh Homes Limited1740%74—
Killross Properties Limited510726%6712
Kilcullenbridge Developments Limited1670%67—
Tapeford Limited1580%58—
Balyna Hotel Limited1540%54—
Nua Healthcare Services Limited1500%50—
Debussy Properties Limited1500%50—
Springwood Limited1480%48—
Clúid Housing1340%34—
Kestorra Limited24745%26—
O’Flynn Construction (Dublin) Limited1250%25—
Mayra Homes Limited1200%20—
Clonmel Enterprises Limited1160%16—
Liffeybridge Homes Limited1140%14—
Andrews Construction Limited1140%14—
MA Tudor Investments Limited1140%14—
Ascot Construction Limited1120%12—

Permission, no start 53 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Railpark Maynooth Co. Kildare 256111958110 Sept 2026Not started lapses in 5 yearsMaynooth
Capdoo 1930463226827 Oct 2019Not started lapses in 3 yearsCúl na Mucos
“Harpur Lane” 246005524329 Apr 2024Not started lapses in 3 yearsLeixlip
Devoy Barracks 2231327621913 Oct 2022Not started lapses within a yearNaas
Dublin Road 266046921329 Sept 2026Not started lapses in 5 yearsGallows Glen
Parson Street 25608771952 Jun 2026Not started lapses in 5 yearsMaynooth
New Abbey Road 246132715218 Sept 2025Not started lapses in 4 yearsKilcullen
Southgreen Road Kildare Co. Kildare 266024813631 Aug 2026Not started lapses in 5 years
Mill Street 24607741156 Jan 2025Not started lapses in 3 yearsMaynooth
R148 25613479528 Jul 2026Not started lapses in 5 yearsSpin Bridge
Oak Church 25605358827 Aug 2025Not started lapses in 4 years
Whitelands East 2110338728 Jun 2023Not started lapses in 2 years
Kilwoghan Woods 2560988763 Dec 2025Not started lapses in 4 yearsCelbridge
Shanrath 25601797424 Nov 2025Not started lapses in 4 years
Naas Road 25608046718 Dec 2025Not started lapses in 4 years
Barretstown Castle 2213876028 Apr 2023Not started lapses in 2 yearsNaas
An Post Depot 2461273586 May 2025Not started lapses in 4 yearsNaas
Oldtown 24603715722 Oct 2025Not started lapses in 4 yearsCelbridge
R148 25613065528 Jul 2026Not started lapses in 5 yearsBoycetown
Moyvalley Hotel & Golf Resort 221498546 Nov 2023Not started lapses in 2 years
Rathangan Demesne 25605405023 Mar 2026Not started lapses in 4 years
Prosperous Road 242455023 Oct 2024Not started lapses in 3 yearsClane
Oldtown Demesne 23794822 May 2023Not started lapses within a yearNaas
Whitelands East 24613234425 Mar 2025Not started lapses in 3 years
Station Road 23603724014 Nov 2024Not started lapses in 3 yearsByrnes Crossroads
Parklands Grove 211108403 Oct 2022Not started lapses in 6 yearsMaynooth
58-67 Leinster Street & Nelson's Yard 2013973821 Dec 2021Not started lapses in 3 years
Celbridge Lodge 26603813717 Sept 2026Not started lapses in 5 yearsCelbridge
Dominican Lands 22985344 Aug 2023Not started lapses in 2 years
Newtown 215862818 Apr 2023Not started lapses in 2 years
Ballitore 2561216265 May 2026Not started lapses in 5 yearsBallitore
Caragh Village 23601822514 Jan 2025Not started lapses in 3 yearsCarragh
Whitelands East 24610232315 Jan 2025Not started lapses in 2 yearsKildare
Sallins Road 26606362011 Sept 2026Not started lapses in 3 yearsAlexandra Bridge
Curragh Farm 25600252010 Dec 2025Not started lapses in 4 years
Jigginstown 24606341926 Aug 2025Not started lapses in 4 yearsNaas
Kildare Road 236731725 Jun 2024Not started lapses in 3 years
Canal Harbour 23602851625 Jun 2025Not started lapses in 4 years
Piercetown 221003165 Oct 2023Not started lapses in 2 yearsByrnes Crossroads
Glebe House 2114171510 Oct 2023Not started lapses in 2 yearsMaynooth
Ferns Bridge 23152153 Jul 2023Not started lapses in 2 years
Ferns Bridge 25606581423 Mar 2026Not started lapses in 4 years
Sallins Wharf Osberstown Drive and Sallins Pier 2461359148 Dec 2025Not started lapses in 4 yearsNaas
Sallins Road 232021430 Oct 2024Not started lapses in 3 yearsNaas
Capdoo 241401430 Jul 2024Not started lapses in 3 yearsClane
Cooleragh East 226621418 Jan 2023Not started lapses within a yearCoolearagh
Steeple View 23603281210 Jun 2024Not started lapses in 3 years
Mount View 251891125 Sept 2026Not started lapses in 5 yearsLeixlip
Oak Church 25607401117 Nov 2025Not started lapses in 4 years
Curragh Grange House 24609901117 Apr 2025Not started lapses in 4 years
Newtown Way 2560256108 Apr 2026Not started lapses in 5 yearsNaas
Curryhills 2351012 Feb 2024Not started lapses in 2 yearsProsperous
Market Square 2213021015 May 2023Not started lapses in 2 yearsNewbridge

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KILDARE' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 3 Oct 2026, 23:01
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.03 Oct 2026, 23:01open
An Coimisiún Pleanála case listCC-BY-4.03 Oct 2026, 23:01open
Building Control Management System commencement noticesCC-BY-4.03 Oct 2026, 23:01open

Recomputed weekly from the store; last built 3 Oct 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.