Permitted, not started · Limerick · grants of 10+ homes since 2017

Limerick: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

10,310 homes in 183 sites of 10 or more have been granted permission in Limerick since 2017. A commencement notice was lodged for 37% of them. 4,911 still have a live permission and no start; 441 of those lapse within a year, and 813 have already lapsed.

10,310
homes permitted · 183 sites
37%
started · 3,827 homes
4,911
not started · live permission
441
lapse within 12 months
813
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
201746871%020
20182573463%0274
20191758265%49153
20201354056%83156
20211565770%30164
2022251,45357%58446
2023251,21939%744
2024201,18357%511
2025202,1527%2,012
2026191,7224%898

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 90% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Groody Developments Limited11,4000%1,400
The Land Development Agency12850%285
SHD - Voyage Properties Limited12330%233
Riverpoint Construction Limited631831%219
Tergnum Properties Limited11390%139
Loughmore Healthcare No.2 Limited11300%130
Voyage Property Limited11260%126
A&R Supplies (Limerick) Limited11150%115
Sonnervale Limited214521%114
Signature Trustee Services Limited11110%111
Clonshire Construction Limited11110%111
Diceros Ventures Limited31520%10349
Dwellings Developments Adare Limited1990%99
Can2 Investments Limited1840%84
Dwellings Developments Castletroy Limited211633%78
Thanos Securities Limited1760%76
Ballygrennan Homes Limited1740%74
Dwellings Developments Cois na Cille Limited317116%6975
HRP Construction Limited1680%68
DW Raheen Developments Limited1580%58
EI-SUB Limited1560%56
Rockspring Developments Limited26316%53
Jada Projects Limited1500%50
Datcha Construction Limited412938%4931
Kirkland Investments Limited24510%48
Indus Ventures Limited1480%48
Tinwat Holdings Limited. (part of the Whitebox Group) in partnership with Cluid Housing211961%46
SHD - The Clonmacken Partnership1440%44
Michael Madden & Son Limited1410%41
McCarthy & Woulfe Limited1410%41

Work started 82 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Ballykeeffe 223131243841 Aug 2022Started notice 24 Apr 2024
Old Dublin Road 22121620217 Jan 2023Started notice 27 Dec 2024
Dromdarrig 21800019113 Jul 2021Started notice 29 Jul 2026
Ardhu House 2355716719 Apr 2024Started notice 4 Sept 2025
Golf Links Road 236084212219 Jan 2024Started notice 20 Dec 2024
Clonmacken 1747011021 Feb 2019Started notice 3 Aug 2020
Clonconane 24600329920 Aug 2024Started notice 20 Aug 2025
Bloodmill Road 18434996 Nov 2018Started notice 21 Oct 2020
Newtown 191236924 Mar 2021Started notice 7 Jul 2023
Knockhill 199709230 Apr 2020Started notice 10 Apr 2023
Newtown 195479028 May 2020Started notice 26 May 2022
Newtown 2111528920 Apr 2022Started notice 11 Apr 2024
Coolbane & Coolreiry 23608667412 Jun 2024Started notice 31 Dec 2024
Ballygrennan 23609517327 Mar 2024Started notice 4 Jun 2026
Mungret Gate 2112167222 Jul 2022Started notice 20 Apr 2024
Skehacreggan 23606156615 Jan 2024Started notice 22 Apr 2024
Brú na Gruadán 201074636 May 2021Started notice 1 Jun 2023
Churchtown 228405726 Jun 2023Started notice 31 Jan 2024
Skagh 222675612 Oct 2022Started notice 8 Dec 2023
Barnakyle 2561228556 May 2026Started notice 14 Jul 2026
Ros Mor Estate 181243534 Sept 2019Started notice 28 Apr 2021
Ballyveloge 2213185224 Oct 2023Started notice 5 Feb 2025
Coolbane 195185121 Dec 2020Started notice 14 Jan 2022
Walkers Road 19492512 Oct 2019Started notice 20 Jan 2021
Ballyanrahan East 182004911 Dec 2018Started notice 9 Dec 2022
Newtown 181104434 Jun 2019Started notice 7 Jul 2023
Sycamore Avenue 1880074312 Sept 2018Started notice 30 Apr 2020
Clonmacken 1880084312 Sept 2018Started notice 24 Sept 2019
Ash Hill 24607884215 Jul 2025Started notice 6 Apr 2026
Newtown 2360260385 Oct 2023Started notice 8 Nov 2023
Towlerton 22950385 Sept 2023Started notice 18 Sept 2026
Newtown 186983821 Nov 2018Started notice 18 Sept 2019
Bloodmill Road 1812703729 May 2019Started notice 25 May 2021
Speakers Corner 2280163621 Nov 2022Started notice 25 Sept 2024
Mungret Gate 2011953523 Jun 2021Started notice 8 Apr 2022
Newtown 1811053519 Sept 2019Started notice 6 Jul 2023
Gortboy 179263329 May 2018Started notice 11 Dec 2020
Sandybrook House 25601513127 Nov 2025Started notice 12 May 2026
Newtown 20256318 Dec 2020Started notice 26 May 2021
Caislean Nua 1855314 Jul 2018Started notice 8 Aug 2018
Pallas 243523017 Sept 2025Started notice 22 Dec 2025
Flag Lane Sullivans Lane Curry Lane 211640308 Mar 2022Started notice 11 Jul 2024
Slí na Manach 204672929 Jan 2021Started notice 11 Oct 2021
Sexton Street North 2211892824 Oct 2023Started notice 20 Feb 2026
Newtown 21350283 Dec 2021Started notice 25 Mar 2022
Skehacreggaun 2113282710 Jun 2022Started notice 30 May 2022
Dalgaish Park 1980032710 Sept 2019Started notice 18 Jul 2022
Newtown 211400269 Jun 2022Started notice 1 Jul 2024
Lower Park Road 215202622 Apr 2022Started notice 17 Jul 2024
Newtown 24601462521 May 2024Started notice 13 Jun 2024
Newcastle 211475233 May 2022Started notice 15 Aug 2022
Moore Street 23529223 Sept 2024Started notice 9 Oct 2025
Newtown 2360044229 Aug 2023Started notice 23 Oct 2023
Junction of the Childers Road /Greenfield Road 23600252122 Mar 2023Started notice 23 Oct 2025
Mungret Gate 24607042021 May 2025Started notice 4 Aug 2025
St. Anne's 227932013 Sept 2022Started notice 31 Dec 2024
Glenview 1880022014 May 2018Started notice 18 Mar 2020
Drominbeg 178002019 Oct 2017Started notice 21 May 2021
Slí na Manach 184651918 Sept 2018Started notice 16 Jul 2020
Main Street 2460568177 Mar 2025Started notice 9 Oct 2025

160 of 82Next 60

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'LIMERICK' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.