PlanningRegister.ie
Permitted, not started · Mayo · grants of 10+ homes since 2017

Mayo: homes with planning permission that nobody has started

Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness

1,904 homes in 60 sites of 10 or more have been granted permission in Mayo since 2017. A commencement notice was lodged for 54% of them. 774 still have a live permission and no start; 51 of those lapse within a year, and 52 have already lapsed.

1,904
homes permitted · 60 sites
54%
started · 1,031 homes
774
not started · live permission
51
lapse within 12 months
52
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
2019312792%010
2020430797%010
20214450%1332
2022311768%38—
202336368%20—
20241536448%191—
20251342958%180—
20261545216%332—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 27 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 42% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
MGB Land Holdings Limited3820%82—
Wyckam Limited618257%6612
Carrabaun Developments Limited1520%52—
MVS Construction Limited1320%32—
Manozo Limited1290%29—
P McHugh & Sons Limited1270%27—
EMW Developments Limited1210%21—
Achill Formwork & Construction Limited1190%19—
Avvic Private Limited1190%19—
Martin Moran Builders Limited1160%16—
Soir Siar Investments Limited1160%16—
Rosshaven Developments Limited1150%15—
Larchbury Properties Limited1150%15—
Sharakah One Limited1150%15—
Kamport Limited1130%13—
P & D Lydon Limited1120%12—
CQD Limited1120%12—
KILMOVEE COMMUNITY HOUSING1100%10—
Knocknalyre Limited152100%0—
Sayvale 19 Limited142100%0—
Cappaglen Developments Limited132100%0—
EBV Construction Limited EBV Construction Limited126100%0—
Newpark Developments Limited120100%0—
BECKETT DEVELOPMENTS LIMITED117100%0—
BRENDAN BYRNE & SON Limited1100%010
TML PROPERTIES1100%010
BECKETT DEVELOPMENTS1100%010

Lapses within a year 3 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
NEWPORT ROAD 22912822 Aug 2022Lapsing lapses in 11 months
ARD CAHER 21701138 Dec 2021Lapsing lapses in 2 months
KILMOVEE 2111241018 Jul 2022Lapsing lapses in 10 months

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'MAYO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.026 Sept 2026, 07:08open
An Coimisiún Pleanála case listCC-BY-4.026 Sept 2026, 07:08open
Building Control Management System commencement noticesCC-BY-4.026 Sept 2026, 07:08open

Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness