Monaghan: homes with planning permission that nobody has started
Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness
1,073 homes in 35 sites of 10 or more have been granted permission in Monaghan since 2017. A commencement notice was lodged for 43% of them. 474 still have a live permission and no start; 56 of those lapse within a year, and 91 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 1 | 43 | 0% | 0 | 43 |
| 2018 | 1 | 20 | 100% | 0 | — |
| 2019 | 4 | 120 | 82% | 0 | 22 |
| 2020 | 4 | 150 | 55% | 42 | 26 |
| 2021 | 2 | 73 | 82% | 13 | — |
| 2022 | 4 | 67 | 18% | 55 | — |
| 2023 | 2 | 59 | 37% | 37 | — |
| 2024 | 1 | 18 | 100% | 0 | — |
| 2025 | 9 | 310 | 28% | 222 | — |
| 2026 | 7 | 213 | 30% | 105 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 26 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 93% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Geda Construction Company Limited | 4 | 128 | 40% | 77 | — |
| Clarlan Limited | 2 | 72 | 0% | 72 | — |
| B & C Contractors Limited | 2 | 99 | 43% | 56 | — |
| Callan Group Limited | 1 | 42 | 0% | 42 | — |
| McGuigan Builders Limited | 1 | 37 | 0% | 37 | — |
| Shadowfall Limited | 1 | 30 | 0% | 30 | — |
| Forever Warm Homes Limited | 1 | 27 | 0% | 27 | — |
| Park Edge Contracting Limited | 1 | 13 | 0% | 13 | — |
| PDES Limited | 1 | 13 | 0% | 13 | — |
| Hadabo Developments Limited | 1 | 12 | 0% | 12 | — |
| Corvalley Enterprises Limited | 1 | 12 | 0% | 12 | — |
| Thomas Agnew & Sons | 1 | 10 | 0% | 10 | — |
| Moffett Investment Holdings | 1 | 72 | 100% | 0 | — |
| Berwat Construction Limited | 2 | 70 | 100% | 0 | — |
| Glassford Developments Limited | 1 | 60 | 100% | 0 | — |
| Connolly Partnership | 1 | 44 | 0% | 0 | — |
| JC Developments (NI) Limited | 1 | 43 | 100% | 0 | — |
| Monaghan County Council | 1 | 43 | 0% | 0 | 43 |
| Greenbriar Developments Limited | 1 | 41 | 100% | 0 | — |
| Ballymar Developments Limited | 1 | 26 | 0% | 0 | 26 |
| ANG Property Limited | 1 | 22 | 0% | 0 | 22 |
| RPK Construction Limited | 1 | 22 | 100% | 0 | — |
| Oaklee Housing | 1 | 20 | 100% | 0 | — |
| Eakin Developments Limited | 1 | 16 | 100% | 0 | — |
| T & S Plant Hire Limited | 1 | 14 | 100% | 0 | — |
| Tydavnet Construction Limited | 1 | 12 | 100% | 0 | — |
Work started 14 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Kilmactrasna & Mullanarry 2560144 | 72 | 29 Sept 2025 | Started notice 21 Aug 2026 | |
| Nafarty/Cloghvalley Upper 20530 | 60 | 8 Dec 2021 | Started notice 6 Feb 2024 | |
| Shercock Road 19322 | 52 | 17 Jun 2020 | Started notice 3 Nov 2021 | |
| Nafarty/Cloghvally Upper 2560311 | 43 | 19 Jan 2026 | Started notice 29 Jun 2026 | |
| Onomy and Annahale Townlands 18368 | 43 | 27 Feb 2019 | Started notice 22 May 2024 | |
| Corr An Tobair Estate Nafarty 19159 | 41 | 22 Oct 2019 | Started notice 16 Nov 2020 | |
| Coill Darach 20290 | 30 | 26 Nov 2020 | Started notice 17 Jan 2022 | |
| Sean Mhuileann 22105 | 22 | 1 Sept 2023 | Started notice 23 Apr 2024 | |
| Monneill 2560326 | 21 | 30 Jan 2026 | Started notice 3 Aug 2026 | |
| Liseggerton 1896 | 20 | 6 Jun 2018 | Started notice 6 Jan 2020 | |
| Castle Park Development 2360152 | 18 | 12 Aug 2024 | Started notice 20 Sept 2024 | |
| Drummond Otra 2460137 | 16 | 14 Feb 2025 | Started notice 3 Jul 2026 | |
| Emyvale, Co. Monaghan 19210 | 14 | 22 Nov 2019 | Started notice 28 Apr 2021 | |
| Tedavnet 21452 | 12 | 10 Jan 2022 | Started notice 17 May 2022 |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'MONAGHAN' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |