PlanningRegister.ie
Permitted, not started · Offaly · grants of 10+ homes since 2017

Offaly: homes with planning permission that nobody has started

Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness

2,449 homes in 53 sites of 10 or more have been granted permission in Offaly since 2017. A commencement notice was lodged for 49% of them. 929 still have a live permission and no start; 142 of those lapse within a year, and 308 have already lapsed.

2,449
homes permitted · 53 sites
49%
started · 1,192 homes
929
not started · live permission
142
lapse within 12 months
308
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
20182217100%0—
2019528467%094
2020519180%039
2021826035%7890
2022822041%4485
20231036246%196—
2024433857%146—
202563020%302—
2026527533%163—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 25 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 83% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Arden Square Development Limited21960%196—
TULLAMORE VITA STILO Limited and A CAPITAL HOMES21160%9818
JAMES SPOLLEN LIMITED1950%95—
RIVERPOINT CONSTRUCTION LIMITED1780%78—
Collins Lane Housing Development Limited315068%48—
Offaly Solar Energy AS Limited1480%48—
Fitzpatrick & Heavey Homes Limited27951%39—
SOPHIA HOUSING ASSOCIATION CLG1280%28—
LEAMORE CONSTRUCTION LIMITED1250%25—
JOHN FLANAGAN DEVELOPMENTS Limited313567%1926
SPA ROAD HOMES LIMITED1190%19—
CODD PROPERTY HOLDINGS LIMITED538564%0139
Newlyn Homes Limited322581%043
TULLAMORE VITA STILO Limited T and A CAPITAL HOMES199100%0—
FERNSIDE HOMES Limited175100%0—
BEECH AVENUE PROPERTIES LIMITED161100%0—
GLENVEAGH HOMES Limited24075%010
SMART 2 MANAGEMENT VENTURES LIMITED1390%039
SAMLEIGH PROPERTIES Limited237100%0—
PMB CONSTRUCTION Limited1220%022
N.C.E. DEVELOPMENTS Limited121100%0—
GREYPOST DEVELOPMENTS LIMITED118100%0—
BROUDER BROS STEEL LIMITED116100%0—
LIAM WALSH & COMPANY LIMITED116100%0—
ROBIN INVESTMENTS FR. MCWEY STREET EDENDERRY Limited1110%011

Permission lapsed 10 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
EISCIR MEADOWS / NORBURY WOODS 185556815 Aug 2019Lapsed lapsed 2 years ago
EISCIR MEADOWS/NORBURY WOODS 211415124 Aug 2021Lapsed lapsed 2 years ago
TYRRELLS BROOK 22864324 Jun 2022Lapsed lapsed 11 months ago
BOG ROAD 191423924 Mar 2020Lapsed lapsed 3 years ago
SRAH ROAD 183302612 Apr 2019Lapsed lapsed 2 years ago
EDENDERRY SHOPPING CENTRE 223228 Sept 2022Lapsed lapsed 3 years ago
EISCIR MEADOWS/NORBURY WOODS 22532011 Aug 2022Lapsed lapsed 3 years ago
CLARA ROAD 211741823 Aug 2021Lapsed lapsed recently
EDENDERRY CO. OFFALY 203141110 Jun 2021Lapsed lapsed 4 months ago
TULLAMORE EDUCATE TOGETHER NATIONAL SCHOOL 20466105 Jan 2021Lapsed lapsed 4 years ago

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'OFFALY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.026 Sept 2026, 07:08open
An Coimisiún Pleanála case listCC-BY-4.026 Sept 2026, 07:08open
Building Control Management System commencement noticesCC-BY-4.026 Sept 2026, 07:08open

Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness