Offaly: homes with planning permission that nobody has started
Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness
2,449 homes in 53 sites of 10 or more have been granted permission in Offaly since 2017. A commencement notice was lodged for 49% of them. 929 still have a live permission and no start; 142 of those lapse within a year, and 308 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2018 | 2 | 217 | 100% | 0 | — |
| 2019 | 5 | 284 | 67% | 0 | 94 |
| 2020 | 5 | 191 | 80% | 0 | 39 |
| 2021 | 8 | 260 | 35% | 78 | 90 |
| 2022 | 8 | 220 | 41% | 44 | 85 |
| 2023 | 10 | 362 | 46% | 196 | — |
| 2024 | 4 | 338 | 57% | 146 | — |
| 2025 | 6 | 302 | 0% | 302 | — |
| 2026 | 5 | 275 | 33% | 163 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 25 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 83% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Arden Square Development Limited | 2 | 196 | 0% | 196 | — |
| TULLAMORE VITA STILO Limited and A CAPITAL HOMES | 2 | 116 | 0% | 98 | 18 |
| JAMES SPOLLEN LIMITED | 1 | 95 | 0% | 95 | — |
| RIVERPOINT CONSTRUCTION LIMITED | 1 | 78 | 0% | 78 | — |
| Collins Lane Housing Development Limited | 3 | 150 | 68% | 48 | — |
| Offaly Solar Energy AS Limited | 1 | 48 | 0% | 48 | — |
| Fitzpatrick & Heavey Homes Limited | 2 | 79 | 51% | 39 | — |
| SOPHIA HOUSING ASSOCIATION CLG | 1 | 28 | 0% | 28 | — |
| LEAMORE CONSTRUCTION LIMITED | 1 | 25 | 0% | 25 | — |
| JOHN FLANAGAN DEVELOPMENTS Limited | 3 | 135 | 67% | 19 | 26 |
| SPA ROAD HOMES LIMITED | 1 | 19 | 0% | 19 | — |
| CODD PROPERTY HOLDINGS LIMITED | 5 | 385 | 64% | 0 | 139 |
| Newlyn Homes Limited | 3 | 225 | 81% | 0 | 43 |
| TULLAMORE VITA STILO Limited T and A CAPITAL HOMES | 1 | 99 | 100% | 0 | — |
| FERNSIDE HOMES Limited | 1 | 75 | 100% | 0 | — |
| BEECH AVENUE PROPERTIES LIMITED | 1 | 61 | 100% | 0 | — |
| GLENVEAGH HOMES Limited | 2 | 40 | 75% | 0 | 10 |
| SMART 2 MANAGEMENT VENTURES LIMITED | 1 | 39 | 0% | 0 | 39 |
| SAMLEIGH PROPERTIES Limited | 2 | 37 | 100% | 0 | — |
| PMB CONSTRUCTION Limited | 1 | 22 | 0% | 0 | 22 |
| N.C.E. DEVELOPMENTS Limited | 1 | 21 | 100% | 0 | — |
| GREYPOST DEVELOPMENTS LIMITED | 1 | 18 | 100% | 0 | — |
| BROUDER BROS STEEL LIMITED | 1 | 16 | 100% | 0 | — |
| LIAM WALSH & COMPANY LIMITED | 1 | 16 | 100% | 0 | — |
| ROBIN INVESTMENTS FR. MCWEY STREET EDENDERRY Limited | 1 | 11 | 0% | 0 | 11 |
Permission lapsed 10 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| EISCIR MEADOWS / NORBURY WOODS 18555 | 68 | 15 Aug 2019 | Lapsed lapsed 2 years ago | |
| EISCIR MEADOWS/NORBURY WOODS 21141 | 51 | 24 Aug 2021 | Lapsed lapsed 2 years ago | |
| TYRRELLS BROOK 2286 | 43 | 24 Jun 2022 | Lapsed lapsed 11 months ago | |
| BOG ROAD 19142 | 39 | 24 Mar 2020 | Lapsed lapsed 3 years ago | |
| SRAH ROAD 18330 | 26 | 12 Apr 2019 | Lapsed lapsed 2 years ago | |
| EDENDERRY SHOPPING CENTRE 223 | 22 | 8 Sept 2022 | Lapsed lapsed 3 years ago | |
| EISCIR MEADOWS/NORBURY WOODS 2253 | 20 | 11 Aug 2022 | Lapsed lapsed 3 years ago | |
| CLARA ROAD 21174 | 18 | 23 Aug 2021 | Lapsed lapsed recently | |
| EDENDERRY CO. OFFALY 20314 | 11 | 10 Jun 2021 | Lapsed lapsed 4 months ago | |
| TULLAMORE EDUCATE TOGETHER NATIONAL SCHOOL 20466 | 10 | 5 Jan 2021 | Lapsed lapsed 4 years ago |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'OFFALY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.