Permitted, not started · Offaly · grants of 10+ homes since 2021

Offaly planning permission: the homes nobody has started

Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness

1,684 homes in 38 sites of 10 or more have been granted permission in Offaly since 2021. A commencement notice was lodged for 44% of them. 802 still have a live permission and no start; 240 of those lapse within a year, and 116 have already lapsed.

1,684
homes permitted · 38 sites
44%
started · 746 homes
802
not started · live permission
240
lapse within 12 months
116
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 3

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Tullamore221,16842%62824051
Birr927354%126——
Edenderry724345%48—65

By year granted

Granted inSitesHomesStartedNot startedLapsed
2021413161%051
2022825758%4465
20231036249%186—
2024433857%146—
2025630219%244—
2026629431%182—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 15 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 59% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Arden Square Development Limited21960%196—
JAMES SPOLLEN LIMITED1950%95—
Collins Lane Housing Development Limited315068%48—
Fitzpatrick & Heavey Homes Limited1390%39—
SOPHIA HOUSING ASSOCIATION CLG1280%28—
LEAMORE CONSTRUCTION LIMITED1250%25—
JOHN FLANAGAN DEVELOPMENTS Limited210983%19—
SPA ROAD HOMES LIMITED1190%19—
Newlyn Homes Limited213568%043
ROCKTOP ASSET MANAGEMENT LIMITED198100%0—
PMB CONSTRUCTION Limited1220%022
CODD PROPERTY HOLDINGS LIMITED120100%0—
GREYPOST DEVELOPMENTS LIMITED118100%0—
TULLAMORE VITA STILO LIMITED and A CAPITAL HOMES118100%0—
SAMLEIGH PROPERTIES Limited117100%0—

Lapses within a year 4 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Arden Road 26601589823 Jun 2026Lapsing lapses in 4 monthsTullamore
Arden 25603149820 Oct 2025Lapsing lapses in 4 monthsTullamore
KILCOURSEY 21584269 Aug 2022Lapsing lapses in 9 monthsTullamore
TULLAMORE 213761825 Jul 2022Lapsing lapses in 9 monthsTullamore

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'OFFALY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.06 Nov 2026, 23:00open
An Coimisiún Pleanála case listCC BY 4.06 Nov 2026, 23:00open
Building Control Management System commencement noticesCC BY 4.06 Nov 2026, 23:00open

Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.