Permitted, not started · Sligo · grants of 10+ homes since 2017

Sligo: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

1,818 homes in 38 sites of 10 or more have been granted permission in Sligo since 2017. A commencement notice was lodged for 51% of them. 809 still have a live permission and no start; 34 of those lapse within a year, and 37 have already lapsed.

1,818
homes permitted · 38 sites
51%
started · 926 homes
809
not started · live permission
34
lapse within 12 months
37
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
20181180%018
2019188100%0
2020414187%019
20211340%34
2022526940%162
2023420774%53
2024532739%200
2025949666%134
202682380%226

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 27 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 81% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Brava Capital Limited11040%104
Cosmo Developments Limited1740%74
SDCH Properties Limited1580%58
Siara Developments Limited1570%57
Mulryan Construction Limited Grallaghmore1530%53
Eminance Homes Limited1510%51
KDM Construction Limited1350%35
Westcoast Quality Homes Limited1340%34
Travac Developments Limited1320%32
Teeling Street Development Limited1310%31
Higgins & Keegan Retail Limited1130%13
Housing Association for Integrated Living1130%13
CCMD Developments Limited1120%12
Fermoyle Properties Limited1110%11
Sophia Housing Association Limited1100%10
Novot Holdings Limited2281100%0
Caltragh Construction Limited2158100%0
Carnarvon Limited1127100%0
Knoxpark Developments Limited3123100%0
Carty Contractors Limited159100%0
RCEH Trust1340%0
SPDD Properties Limited134100%0
Kilcawley Building and Civil Engineering (Sligo) Limited1190%019
Parkway Projects Limited116100%0
Altitude Distribution Limited (Cathal O’Connor)115100%0
Tom McNicholas Builders Limited112100%0
McEniffs (Bundoran) Limited1120%0

Lapses within a year 1 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Tonaphubble Road 211903423 Dec 2021Lapsing lapses in 3 months

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'SLIGO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness