Sligo: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
1,818 homes in 38 sites of 10 or more have been granted permission in Sligo since 2017. A commencement notice was lodged for 51% of them. 809 still have a live permission and no start; 34 of those lapse within a year, and 37 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2018 | 1 | 18 | 0% | 0 | 18 |
| 2019 | 1 | 88 | 100% | 0 | — |
| 2020 | 4 | 141 | 87% | 0 | 19 |
| 2021 | 1 | 34 | 0% | 34 | — |
| 2022 | 5 | 269 | 40% | 162 | — |
| 2023 | 4 | 207 | 74% | 53 | — |
| 2024 | 5 | 327 | 39% | 200 | — |
| 2025 | 9 | 496 | 66% | 134 | — |
| 2026 | 8 | 238 | 0% | 226 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 27 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 81% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Brava Capital Limited | 1 | 104 | 0% | 104 | — |
| Cosmo Developments Limited | 1 | 74 | 0% | 74 | — |
| SDCH Properties Limited | 1 | 58 | 0% | 58 | — |
| Siara Developments Limited | 1 | 57 | 0% | 57 | — |
| Mulryan Construction Limited Grallaghmore | 1 | 53 | 0% | 53 | — |
| Eminance Homes Limited | 1 | 51 | 0% | 51 | — |
| KDM Construction Limited | 1 | 35 | 0% | 35 | — |
| Westcoast Quality Homes Limited | 1 | 34 | 0% | 34 | — |
| Travac Developments Limited | 1 | 32 | 0% | 32 | — |
| Teeling Street Development Limited | 1 | 31 | 0% | 31 | — |
| Higgins & Keegan Retail Limited | 1 | 13 | 0% | 13 | — |
| Housing Association for Integrated Living | 1 | 13 | 0% | 13 | — |
| CCMD Developments Limited | 1 | 12 | 0% | 12 | — |
| Fermoyle Properties Limited | 1 | 11 | 0% | 11 | — |
| Sophia Housing Association Limited | 1 | 10 | 0% | 10 | — |
| Novot Holdings Limited | 2 | 281 | 100% | 0 | — |
| Caltragh Construction Limited | 2 | 158 | 100% | 0 | — |
| Carnarvon Limited | 1 | 127 | 100% | 0 | — |
| Knoxpark Developments Limited | 3 | 123 | 100% | 0 | — |
| Carty Contractors Limited | 1 | 59 | 100% | 0 | — |
| RCEH Trust | 1 | 34 | 0% | 0 | — |
| SPDD Properties Limited | 1 | 34 | 100% | 0 | — |
| Kilcawley Building and Civil Engineering (Sligo) Limited | 1 | 19 | 0% | 0 | 19 |
| Parkway Projects Limited | 1 | 16 | 100% | 0 | — |
| Altitude Distribution Limited (Cathal O’Connor) | 1 | 15 | 100% | 0 | — |
| Tom McNicholas Builders Limited | 1 | 12 | 100% | 0 | — |
| McEniffs (Bundoran) Limited | 1 | 12 | 0% | 0 | — |
Permission, no start 18 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Newtownholmes Road 2460198 | 118 | 23 Dec 2024 | Not started lapses in 3 years | |
| Clarion Road 2291 | 104 | 25 Nov 2022 | Not started lapses within a year | |
| Carrownanty 2560484 | 74 | 22 May 2026 | Not started lapses in 5 years | |
| Cullagh More 2460415 | 73 | 17 Oct 2025 | Not started lapses in 4 years | |
| Maghera Td. 2213 | 58 | 16 Aug 2022 | Not started lapses in 4 years | |
| Earls Court 2460077 | 57 | 8 Nov 2024 | Not started lapses in 3 years | |
| Circular Road 2360084 | 53 | 21 Dec 2023 | Not started lapses in 2 years | |
| Cairns Road 2660014 | 51 | 21 Aug 2026 | Not started lapses in 5 years | |
| Fairways Oghambaun Td 2560468 | 35 | 4 Feb 2026 | Not started lapses in 4 years | |
| SwanPoint 2560004 | 32 | 2 Apr 2025 | Not started lapses in 4 years | |
| No. 6 Teeling Street 2560439 | 31 | 26 Jan 2026 | Not started lapses in 4 years | |
| Main Street 2460428 | 18 | 2 Jul 2025 | Not started lapses in 4 years | |
| 3 Lyons Terrace 2660178 | 13 | 4 Aug 2026 | Not started lapses in 5 years | |
| Carrowhubbuck South Inishcrone County Sligo 2460060 | 13 | 18 Dec 2024 | Not started lapses in 3 years | |
| Strandhill Lodge & Hostel and Knocknarea House 2560270 | 12 | 10 Feb 2026 | Not started lapses in 5 years | |
| Bunnanaddan 2360370 | 12 | 23 Sept 2024 | Not started lapses in 3 years | |
| Knappagh More 2460295 | 11 | 30 Sept 2025 | Not started lapses in 5 years | |
| Summerhill 2560282 | 10 | 11 Mar 2026 | Not started lapses in 4 years |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'SLIGO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.