Permitted, not started · Westmeath · grants of 10+ homes since 2017

Westmeath: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

3,836 homes in 75 sites of 10 or more have been granted permission in Westmeath since 2017. A commencement notice was lodged for 58% of them. 1,585 still have a live permission and no start; 32 of those lapse within a year, and 12 have already lapsed.

3,836
homes permitted · 75 sites
58%
started · 2,239 homes
1,585
not started · live permission
32
lapse within 12 months
12
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
2017335100%0
2018411289%012
2019515783%27
20203127100%0
2021828454%131
2022818992%15
2023141,01661%392
2024966286%91
20251268747%362
202695670%567

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 89% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Glenveagh Homes Limited353840%325
Akiyda Limited12570%257
Garrycastle Homes Limited trading as Alanna Homes21210%121
Ballymount Contracting Limited11170%117
Lynx Developments Limited11030%103
Wincove Land Limited313024%99
PF&4Ds Limited1910%91
WHS Property Holdings Limited1810%81
Tiberville Limited1730%73
Lacken Ventures Limited1500%50
BFJ Developments Limited1380%38
Markayla Limited1250%25
Andrews Construction Limited324292%20
Melvin Properties Limited1190%19
Spoutwell Developments1160%16
Lambe Bros1130%13
Mulleady Properties & Co. Limited23667%12
Bower Hall Limited1100%10
Strongly Limited1100%10
Marina Quarter Limited3404100%0
JH Kinnie Limited1127100%0
KDM Construction Limited1100100%0
Lampbell Limited199100%0
Kelbuild Limited179100%0
Brennan & McCann Developments (Coola) Limited272100%0
Mistledale Limited165100%0
Frank Bell & Son Limited165100%0
Blue Ridge Developments Limited162100%0
N.J. Doyne Construction (Ireland) Limited347100%0
Bigwood Properties Limited145100%0

Lapses within a year 2 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Clonmore Shopping Centre 2063081729 Jul 2021Lapsing lapses in 8 months
39 & 41 Oliver Plunkett Street 213081511 Mar 2022Lapsing lapses in 6 months

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WESTMEATH' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.