PlanningRegister.ie
Permitted, not started · Westmeath · grants of 10+ homes since 2017

Westmeath: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

3,836 homes in 75 sites of 10 or more have been granted permission in Westmeath since 2017. A commencement notice was lodged for 58% of them. 1,585 still have a live permission and no start; 32 of those lapse within a year, and 12 have already lapsed.

3,836
homes permitted · 75 sites
58%
started · 2,239 homes
1,585
not started · live permission
32
lapse within 12 months
12
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
2017335100%0
2018411289%012
2019515783%27
20203127100%0
2021828454%131
2022818992%15
2023141,01661%392
2024966286%91
20251268747%362
202695670%567

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 89% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Glenveagh Homes Limited353840%325
Akiyda Limited12570%257
Garrycastle Homes Limited trading as Alanna Homes21210%121
Ballymount Contracting Limited11170%117
Lynx Developments Limited11030%103
Wincove Land Limited313024%99
PF&4Ds Limited1910%91
WHS Property Holdings Limited1810%81
Tiberville Limited1730%73
Lacken Ventures Limited1500%50
BFJ Developments Limited1380%38
Markayla Limited1250%25
Andrews Construction Limited324292%20
Melvin Properties Limited1190%19
Spoutwell Developments1160%16
Lambe Bros1130%13
Mulleady Properties & Co. Limited23667%12
Bower Hall Limited1100%10
Strongly Limited1100%10
Marina Quarter Limited3404100%0
JH Kinnie Limited1127100%0
KDM Construction Limited1100100%0
Lampbell Limited199100%0
Kelbuild Limited179100%0
Brennan & McCann Developments (Coola) Limited272100%0
Mistledale Limited165100%0
Frank Bell & Son Limited165100%0
Blue Ridge Developments Limited162100%0
N.J. Doyne Construction (Ireland) Limited347100%0
Bigwood Properties Limited145100%0

Work started 47 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Rathgowan 2251521319 Jan 2023Started notice 15 Feb 2023
Dublin Road 24603762102 Dec 2024Started notice 12 May 2026
Rathgowan 236027017120 Dec 2023Started notice 13 Sept 2024
Cornamaddy 236037416315 May 2024Started notice 13 Dec 2024
Boreen Bradach 25602341277 Nov 2025Started notice 10 Apr 2026
Ardmore Road 256025910012 Dec 2025Started notice 3 Feb 2026
Charlestown 1961599930 Jul 2020Started notice 18 Jun 2021
Harbour Road/Martin's Lane 216697923 Nov 2022Started notice 29 Mar 2024
Cornamaddy 225777031 Oct 2023Started notice 23 Sept 2024
Hillquarter 23601416519 Jun 2024Started notice 19 Jan 2026
Ardmore Hills Marlinstown 2260036654 Sept 2023Started notice 16 Dec 2024
distributor road serving the Abbeybrook residential developm 24603466218 Feb 2025Started notice 20 Feb 2026
Coosan Link Road 2117628 Nov 2021Started notice 11 Apr 2024
Lower Rd 1871595530 Sept 2019Started notice 4 Jan 2022
Main Street 1771324617 Aug 2018Started notice 8 Mar 2021
Kingscourt 23602364511 Sept 2024Started notice 31 Dec 2024
Lands adjoining Coola Lawns 25163631 Jul 2025Started notice 16 Jul 2025
Lands adjoining Coola Lawns 1962063612 Nov 2019Started notice 31 Oct 2022
Jones Lake Road 207115356 Jan 2021Started notice 31 Aug 2023
Blyry Lower 1871433228 Dec 2018Started notice 6 Mar 2019
Sites 1-10A 23-24 incl & 28-41 inclu 2060733020 Jan 2021Started notice 14 Oct 2022
existing Marist College 23603612816 Dec 2024Started notice 7 Sept 2026
Raistin Court 23603332626 Nov 2024Started notice 22 Jun 2026
Carmelite Monastery 222812626 Jan 2023Started notice 8 Jan 2024
Cluain Lorcain 24600482414 Aug 2024Started notice 30 Sept 2024
Mullingar Road 1862502417 May 2019Started notice 28 Oct 2020
Glenatore 224842227 Nov 2023Started notice 18 Apr 2025
Castlepollard Road 1860342227 Jun 2018Started notice 30 Nov 2020
20 Connaught Street Harry's Lane and 7 Patrick Street 214462119 Oct 2022Started notice 19 Apr 2024
Bellview 22742016 Oct 2022Started notice 10 Apr 2024
Brideswell Street 21646206 Sept 2022Started notice 29 Mar 2024
‘The Moorings’ 2260030187 Sept 2023Started notice 28 Nov 2024
Ashe Road 1961211822 Jan 2020Started notice 16 Jun 2021
Baylough and Bogganfin 21372165 Oct 2021Started notice 9 Apr 2024
Clog Na Leinn 23871518 Sept 2023Started notice 1 Nov 2023
Baylough and Bogganfin 187226151 Jul 2019Started notice 8 May 2019
Castlelost 213711428 Jul 2022Started notice 2 Jul 2025
Springfield Cottages 176081131 Aug 2017Started notice 15 Nov 2021
Killenboylegan 222841213 Mar 2023Started notice 23 Apr 2024
Devinish 221811212 Jan 2023Started notice 17 Apr 2023
Cloon Lara 1761341228 Nov 2017Started notice 16 May 2018
College Street 23134109 Sept 2024Started notice 26 Feb 2026
Rathgarve Estate 21551021 Apr 2022Started notice 13 Dec 2024
Clog Na Leinn 215671020 Apr 2022Started notice 23 May 2022
Main Street 2153109 Dec 2021Started notice 5 Sept 2025
Kingscourt 196224106 Feb 2020Started notice 26 May 2021
Ardmore Hills 1761261019 Dec 2017Started notice 27 May 2019

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WESTMEATH' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness