Permitted, not started · Wexford · grants of 10+ homes since 2017

Wexford: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

5,369 homes in 134 sites of 10 or more have been granted permission in Wexford since 2017. A commencement notice was lodged for 75% of them. 1,186 still have a live permission and no start; 138 of those lapse within a year, and 136 have already lapsed.

5,369
homes permitted · 134 sites
75%
started · 4,047 homes
1,186
not started · live permission
138
lapse within 12 months
136
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
20178356100%0—
20181952298%10—
20191352896%021
20201045887%060
20211673390%2055
20221146864%168—
20232072084%118—
20241035475%88—
20251248478%107—
20261574610%675—

Recent years are still open: a permission granted this year has had months, not years, to start.

Permission, no start 33 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Clonhasten 202511459922 Apr 2026Not started lapses in 5 years
Lyre 202513409911 Mar 2026Not started lapses in 4 years
Rocksborough 202513889811 May 2026Not started lapses in 5 years
Ballyboggan 202504869831 Mar 2026Not started lapses in 5 years
Churchtown 202512817424 Jun 2026Not started lapses in 5 years
Butlersland/Chambersland 202510105016 Jan 2026Not started lapses in 4 years
Oaklands 20260190444 Sept 2026Not started lapses in 5 years
Ballyboggan 202306703419 Mar 2024Not started lapses in 2 years
Ballowen or Ramsfortpark 202510863324 Nov 2025Not started lapses in 4 years
Ardcavan 202205843219 Jun 2023Not started lapses in 2 years
Tinnacree 202202473014 Nov 2022Not started lapses within a year
Coolcotts 202404922924 Jul 2024Not started lapses in 3 years
Ballygillane Little 202508692721 Jan 2026Not started lapses in 4 years
Ballowen or Ramsfortpark 202501962414 Jul 2025Not started lapses in 4 years
Crosstown 202601582228 Aug 2026Not started lapses in 5 years
Stonybatter 20251399221 Jul 2026Not started lapses in 5 years
St. John's 202109582020 Dec 2021Not started lapses in 2 years
Litter More 202113021913 Jul 2023Not started lapses in 2 years
New Ross 20250321188 Apr 2026Not started lapses in 5 years
Ballytramon 20221663178 Mar 2023Not started lapses within a year
Coolrainey 202305801616 Aug 2023Not started lapses in 2 years
Coolcots 202413501530 Sept 2025Not started lapses in 4 years
Rocksborough 202213361411 Jan 2023Not started lapses within a year
Mulgannon 202507631326 Nov 2025Not started lapses in 4 years
Lake/Bridgetown South 202310201312 Feb 2024Not started lapses in 2 years
Ballyphillip 202601421219 Aug 2026Not started lapses in 5 years
Ballygillane Big 202602381217 Apr 2026Not started lapses in 5 years
Ballycrane 202501131215 Oct 2025Not started lapses in 4 years
Townparks 202009161225 Jan 2024Not started lapses in 2 years
New Ross 202412721014 Apr 2025Not started lapses in 4 years
Rosetown 202215271014 Apr 2023Not started lapses in 2 years
Ballymurn Upper 20220768101 Feb 2023Not started lapses within a year
BALLYGORMAN 201713791020 Mar 2018Not started lapses in 4 years

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WEXFORD' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.