Permitted, not started · Wicklow · grants of 10+ homes since 2021

Wicklow planning permission: the homes nobody has started

Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness

7,544 homes in 114 sites of 10 or more have been granted permission in Wicklow since 2021. A commencement notice was lodged for 50% of them. 3,517 still have a live permission and no start; 287 of those lapse within a year, and 117 have already lapsed.

7,544
homes permitted · 114 sites
50%
started · 3,782 homes
3,517
not started · live permission
287
lapse within 12 months
117
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 6

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Wicklow402,80862%9036099
Bray East1394122%731158—
Baltinglass211,72656%72869—
Arklow1290923%696——
Greystones2070760%254——
Bray West845351%205—18

By year granted

Granted inSitesHomesStartedNot startedLapsed
2021745039%158117
2022281,71392%129—
20231861989%69—
2024171,70235%1,113—
2025181,93336%1,243—
2026261,12717%805—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 61% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Keldrum Limited368148%352—
Cairn Homes Properties Limited369152%329—
Avonvard Limited11780%178—
Shankill Property Investments Limited11250%125—
DL Residential Properties Limited217650%88—
Rathnew Partnership1880%88—
Certain Assets of Dawnhill and Windhill Limited1860%86—
Beakonshaw Hill Limited1850%85—
Windlynn Limited & Two Mile House Construction Limited1690%69—
Lukal Limited1600%60—
Knockinver Limited1320%32—
Bray Property Development Limited1290%29—
Dungrey Limited1210%21—
Manabard (Holdings) Limited1150%15—
Esmonde Partnership1140%14—
Lidl Ireland GmbH1120%12—
Rycroft RW Limited29188%11—
Tack Packaging (2000) Limited1110%11—
Gilkerry Ventures Limited222095%10—
Cedarbrick Retail Developments Limited313192%10—
Marshall Yards Development Company Limited1269100%0—
Drumakilla Limited2155100%0—
Glenveagh Homes Limited2149100%0—
Wickow County Council1106100%0—
Broomhall Estates Limited2102100%0—
Kingsbridge Design Consultancy Limited1990%099
Conor Furey & Associates Limited189100%0—
Wicklow County Council27175%018
Rockfield New Homes Springmount Limited161100%0—
Andrews Construction Limited159100%0—

Lapses within a year 4 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Bray Golf Club Lands SH2021031259 Dec 2021Lapsing lapses within a monthBray East
Kilmalum Road 2110686919 Sept 2022Lapsing lapses in 10 monthsBaltinglass
Togher More 224596012 Sept 2022Lapsing lapses in 10 monthsWicklow
5 Albert Avenue 214703324 Nov 2021Lapsing lapses within a monthBray

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WICKLOW' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.06 Nov 2026, 23:00open
An Coimisiún Pleanála case listCC BY 4.06 Nov 2026, 23:00open
Building Control Management System commencement noticesCC BY 4.06 Nov 2026, 23:00open

Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.