Wicklow: homes with planning permission that nobody has started
Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness
10,033 homes in 167 sites of 10 or more have been granted permission in Wicklow since 2017. A commencement notice was lodged for 53% of them. 3,674 still have a live permission and no start; 905 of those lapse within a year, and 578 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 4
| Local electoral area | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Greystones | 29 | 1,584 | 43% | 747 | 470 | 124 |
| Baltinglass | 31 | 2,105 | 62% | 694 | 69 | 64 |
| Bray East | 16 | 971 | 14% | 480 | 207 | 17 |
| Bray West | 15 | 635 | 60% | 205 | — | 50 |
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 9 | 216 | 85% | 0 | 32 |
| 2018 | 12 | 565 | 92% | 0 | 47 |
| 2019 | 19 | 980 | 69% | 0 | 307 |
| 2020 | 17 | 1,072 | 39% | 503 | 156 |
| 2021 | 15 | 829 | 65% | 257 | 36 |
| 2022 | 27 | 1,616 | 86% | 232 | — |
| 2023 | 16 | 595 | 88% | 69 | — |
| 2024 | 16 | 1,492 | 24% | 1,136 | — |
| 2025 | 16 | 1,872 | 31% | 955 | — |
| 2026 | 20 | 796 | 18% | 522 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 78% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Cairn Homes Properties Limited | 6 | 1,335 | 34% | 755 | 124 |
| Keldrum Limited | 2 | 619 | 43% | 352 | — |
| Avonvard Limited | 1 | 178 | 0% | 178 | — |
| Shankill Property Investments Limited | 2 | 466 | 0% | 125 | — |
| Pathway Homes Limited | 1 | 107 | 0% | 107 | — |
| Benduff Ireland Limited | 1 | 99 | 0% | 99 | — |
| Kingsbridge Design Consultancy Limited | 1 | 99 | 0% | 99 | — |
| DL Residential Properties Limited | 2 | 176 | 50% | 88 | — |
| Rathnew Partnership | 1 | 88 | 0% | 88 | — |
| Certain Assets of Dawnhill and Windhill Limited | 1 | 86 | 0% | 86 | — |
| Beakonshaw Hill Limited | 1 | 85 | 0% | 85 | — |
| Clonmel Enterprises Limited | 1 | 71 | 0% | 71 | — |
| Windlynn Limited & Two Mile House Construction Limited | 1 | 69 | 0% | 69 | — |
| Lukal Limited | 1 | 60 | 0% | 60 | — |
| Shankill Property Investment Limited | 1 | 54 | 0% | 54 | — |
| Wicklow County Council | 18 | 584 | 58% | 53 | 194 |
| Button Real Estate Works Limited | 1 | 49 | 0% | 49 | — |
| Gorteen Way Limited | 1 | 44 | 0% | 44 | — |
| Knockinver Limited | 1 | 32 | 0% | 32 | — |
| Summitpeak Land Holdings Limited | 1 | 30 | 0% | 30 | — |
| ISH New Build Fund Sub Fund of The Platform ICAV | 1 | 30 | 0% | 30 | — |
| Bray Property Development Limited | 1 | 29 | 0% | 29 | — |
| Denver Valley Developments Limited | 1 | 25 | 0% | 25 | — |
| Defigo Holdings 1 Delgany Limited | 1 | 23 | 0% | 23 | — |
| Dungrey Limited | 1 | 21 | 0% | 21 | — |
| Manabard (Holdings) Limited | 1 | 15 | 0% | 15 | — |
| Furey Consulting Engineers Limited | 1 | 14 | 0% | 14 | — |
| Esmonde Partnership | 1 | 14 | 0% | 14 | — |
| Westwings Partnership Limited | 1 | 13 | 0% | 13 | — |
| Lidl Ireland GmbH | 1 | 12 | 0% | 12 | — |
Permission, no start 39 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Tinahask Upper Money Little and Money Big 24325 | 476 | 21 Jan 2025 | Not started lapses in 3 years | |
| Site of c.16.8ha, at Tinakilly 2360219 | 352 | 2 Feb 2024 | Not started lapses in 4 years | Tinakelly Upper |
| townlands of 23689 | 329 | 12 Apr 2024 | Not started lapses in 4 years | Baltinglass |
| Vevay Road and Boghall Road 2446 | 178 | 15 Mar 2024 | Not started lapses in 3 years | Bray West |
| Wicklow Co. Wicklow 2460825 | 107 | 22 Jul 2025 | Not started lapses in 4 years | |
| Bullford 2560623 | 99 | 29 Jul 2026 | Not started lapses in 5 years | Kilcoole |
| Site includes the existing surface car park accessible off S 2560512 | 99 | 24 Jan 2026 | Not started lapses in 5 years | Bray |
| Market Close 2660348 | 88 | 18 Sept 2026 | Not started lapses in 5 years | Baltinglass |
| Ballybeg 2460756 | 88 | 12 Aug 2025 | Not started lapses in 4 years | |
| Market Close 2560319 | 88 | 22 Jul 2025 | Not started lapses in 4 years | Baltinglass |
| Kilbride 23756 | 86 | 5 Apr 2024 | Not started lapses in 3 years | |
| Kindlestown House 23276 | 85 | 26 Jan 2024 | Not started lapses in 3 years | Greystones |
| Newtown Centre/Newtown Square 2560074 | 71 | 10 Feb 2026 | Not started lapses in 5 years | Baltinglass |
| Seapoint Road 22188 | 54 | 4 Oct 2022 | Not started lapses in 3 years | Bray |
| Rockbrae House 25184 | 53 | 6 Oct 2025 | Not started lapses in 4 years | Bray |
| Sea Road Lott Lane 2460586 | 45 | 20 Dec 2024 | Not started lapses in 3 years | Kilcoole |
| Emoclew Road 2560199 | 38 | 8 Oct 2025 | Not started lapses in 4 years | |
| Arklow Shipping premises 23381 | 34 | 18 Aug 2023 | Not started lapses in 3 years | |
| Lamberton 191171 | 33 | 19 Oct 2020 | Not started lapses in 2 years | |
| Upper Main Street 2560756 | 32 | 7 Apr 2026 | Not started lapses in 5 years | |
| Roundwood Caravan and Camping Park 2660004 | 30 | 23 Jun 2026 | Not started lapses in 5 years | |
| Riverside Apartments 2460611 | 30 | 1 Aug 2025 | Not started lapses in 4 years | |
| Everest Centre site 2460793 | 29 | 25 Mar 2025 | Not started lapses in 3 years | Bray East |
| Bray Head House and the former North Wicklow Educate Togethe 2660118 | 25 | 12 May 2026 | Not started lapses in 5 years | Bray East |
| Main Street Newtownmountkennedy Co. Wicklow at the site of ' 2460778 | 25 | 6 Jan 2026 | Not started lapses in 5 years | Newtownmountkennedy |
| Convent Road 23814 | 23 | 17 Apr 2024 | Not started lapses in 3 years | Delgany |
| Burgage Manor 22574 | 21 | 18 Jan 2023 | Not started lapses in 3 years | Baltinglass |
| Powerscourt Arms Hotel 2560908 | 15 | 5 May 2026 | Not started lapses in 5 years | Kilgarron |
| Bawnogues 2660617 | 14 | 21 Aug 2026 | Not started lapses in 5 years | Baltinglass |
| Beechwood House 2560766 | 14 | 27 Jan 2026 | Not started lapses in 4 years | Delgany |
| Downshire Gardens 2560521 | 14 | 9 Dec 2025 | Not started lapses in 4 years | Baltinglass |
| Wicklow 221164 | 14 | 24 Aug 2023 | Not started lapses in 2 years | |
| Westwings 2360305 | 13 | 24 Jun 2024 | Not started lapses in 3 years | Bray |
| Keatingstown Farm 23390 | 13 | 8 Jan 2024 | Not started lapses in 4 years | |
| AO Smite Site 2360133 | 12 | 31 Jan 2024 | Not started lapses in 2 years | Bray West |
| Lorrin Lodge 2560628 | 11 | 11 Nov 2025 | Not started lapses in 4 years | |
| Church Road 2560139 | 11 | 1 Sept 2025 | Not started lapses in 4 years | Delgany |
| Mariners Point 2660557 | 10 | 8 Sept 2026 | Not started lapses in 5 years | |
| Oakmount 2560142 | 10 | 27 May 2025 | Not started lapses in 4 years |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WICKLOW' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.