Tallaght Central: 5 applications lodged, 5 granted, 0 refused in the week to 19 July 2026

Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness

5 planning applications reached the South Dublin County Council register for Tallaght Central in the week of 13 July to 19 July 2026. The 4-week average is 4 applications a week; this week runs 25% above it. 5 of the 5 decisions were grants and 0 were refusals (100% granted). No application this week gives a unit count.

5+25% vs 4-wkapplications lodged
5+67% vs 4-wkdecided · 5 granted, 0 refused
0commencement notices
0appeals · 0 lodged, 0 decided
9deadlines next week

Applications received 5

The 52-week average is 3 applications a week. The observation window on each is five weeks from receipt (article 29 of the 2001 Regulations); the deadline shown is computed from the register date.

DateReferenceAddressTypeUnitsObservations by
16 Jul 2026ED26/0066Old Belgard Road, Belgard, Dublin 24, D24 YK38Declaration of Exemption Sect. 5—20 Aug 2026
17 Jul 2026LRD26A/0004WUnits 66 and 67, Fourth Avenue, Cookstown Industrial Estate, Tallaght, Dublin 24.Permission—21 Aug 2026
14 Jul 2026SD26A/0170W25 Fernwood Way, Springfield, TallaghtPermission—18 Aug 2026
18 Jul 2026SD26B/0131W19, The Crescent, Kingswood Heights, Dublin 24, D24 W8EVPermission—24 Aug 2026
13 Jul 2026SD26B/0327W40, Homelawn Gardens, Tallaght, Dublin, D24 RKP9Permission—17 Aug 2026

Decisions 5

The median time from receipt to decision this week was 49 days; the 2000 Act's s.34(8) default is eight weeks unless further information intervenes. A refusal can be appealed to An Coimisiún Pleanála within four weeks of the decision date.

DateReferenceAddressDecisionUnitsDays
16 Jul 2026ED26/003222, Cul Na Greine, Old Bawn, Tallaght, DublinDeclared exempt—20
14 Jul 2026SD26A/0037W5A, Colbert's Fort Cottages, Tallaght, Dublin 24Grant permission—27
13 Jul 2026SD26B/0238W22 Parkhill Way, Kilnamanagh, Dublin 24Grant permission & grant retention—55
14 Jul 2026SD26B/0239W273, Glenview Park, Tallaght, Dublin, D24 AYX8Grant permission—56
17 Jul 2026SD26B/0264W29, Kingswood Castle, Dublin, D24 YKK6Grant permission—49

Further information 1

1 FI response came back, restarting a four-week decision period.

DateReferenceAddressFI
18 Jul 2026SD26B/0131W19, The Crescent, Kingswood Heights, Dublin 24, D24 W8EVReply received

Against the run rate

PeriodApplications / weekDecisions / weekGrant rateRegister events
This week55100%11
Previous 4 weeks43100%38
Previous 52 weeks3289%459

Grant rate = grants ÷ (grants + refusals); invalidations and further-information requests are not decisions.

Sources: An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices), Council consultation portals, National planning applications feed (iplan / MyPlan), Council meetings (ModernGov), National Planning Application Database, Residential Zoned Land Tax maps · fetched 12 Sept 2026, 02:04
SourceLicenceFetchedLink
An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.012 Sept 2026, 00:05open
Building Control Management System (commencement notices)CC BY 4.011 Sept 2026, 23:29open
Council consultation portalsCC BY 4.012 Sept 2026, 02:04open
National planning applications feed (iplan / MyPlan)CC BY 4.011 Sept 2026, 17:04open
Council meetings (ModernGov)CC BY 4.011 Sept 2026, 21:46open
National Planning Application DatabaseCC BY 4.011 Sept 2026, 20:35open
Residential Zoned Land Tax mapsCC BY 4.012 Sept 2026, 00:23open

Computed 12 Sept 2026 from the register events in the store for 13 Jul 2026 – 19 Jul 2026. Every figure on this page is a count over those events.

All weekly issues · Sources & freshness · canonical /weekly/SDCC/tallaght-central/2026-w29