Kellistown East , Co. Carlow.
- 1 Feb 2018Received
- 30 Jan 2019Conditional
- 25 Feb 2019Appealed
- 23 Sept 2019Appeal: Granted with conditions
- 23 Sept 2019Final grant
- 22 Sept 2029Permission expires
- Status
- Appeal decided — granted
- Decision
- Conditional · 30 Jan 2019
- Council
- Carlow County Council
- Type
- PERMISSION
- Site
- 2.00 ha
- Appeal
- ACP 303821 · Granted with conditions
What’s proposed
Ten year planning permission for the development of an up to 100MW Battery Energy Storage Facility that will provide energy services to national grid. The development will consist of construction and operation of up to 34 metal containers to store up to a project total of up to 100MW (13.2 tons of Lithium lon) sealed battery cells each with entrances, fire supression systems, Heating Ventilation and Air Conditioning systems, Inverters, control systems, other electrical components, security lighting and ancillary infrastructure and all associated works including security fencing and ancillary grid infrastructure on lands at Kellistown East, County Carlow
1823 is a planning application to Carlow County Council for ten year planning permission for the development of an up to 100MW Battery Energy, received on 1 Feb 2018; permission was granted with conditions on 30 Jan 2019.
Planning details
- Reference
- 1823
- Local authority
- Carlow County Council
- Status
- Appeal decided — granted · register status “APPLICATION FINALISED”
- Received
- 1 Feb 2018
- Observations close
- 8 Mar 2018 (closed 3121 days ago)
- Decision due
- 31 Jan 2019 · decided 30 Jan 2019
- Decision
- Conditional on 30 Jan 2019
- Proposed development
- Ten year planning permission for the development of an up to 100MW Battery Energy Storage Facility that will provide energy services to national grid. The development will consist of construction and operation of up to 34 metal containers to store up to a project total of up to 100MW (13.2 tons of Lithium lon) sealed battery cells each with entrances, fire supression systems, Heating Ventilation and Air Conditioning systems, Inverters, control systems, other electrical components, security lighting and ancillary infrastructure and all associated works including security fencing and ancillary grid infrastructure on lands at Kellistown East, County CarlowAs published by the register.
- Site area
- 2.00 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 9 applications within 500 m in the last 5 years
- OpenKellistown East , Co. Carlow
- GrantedKellistown , Tinryland , Carlow
- CommencedBallycurragh Stud , Ballycurragh , Rathoe Tullow
- GrantedGreat Island to Kellis 220kV , Kellistown East , Co. Carlow
- WithdrawnGreat Island to Kellis 220kV OHL circuit between Great Island Substation in the townland of Great Island Co. Wexford and Kellis Substation in the townland of Kellistown East Co. Carlow. Refer to Public Notices for full list of townlands. ,
- Grantedin the townland of Kellistown East , County Carlow
- RefusedRathoe , Co. Carlow
- Appeal decidedKellistown East , Co. Carlow
Show all 9
Appeal
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
- Radon risk area · 1
Provenance
Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 168511). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/CarlowCC/AppFileRefDetails/1823/0.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |