Check my streetWhat’s proposed
Construction of two plant rooms for operating the storm gates permitted by planning permission ref. 12/00651. One of the plant rooms will be located on Duffy's Pier, the other at the outer end of the breakwater pier will be the main control room for the operation of the storm gates
Planning details
- Reference
- 14/582
- Local authority
- Cork County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 9 Oct 2014
- Observations close
- 13 Nov 2014 (closed 4345 days ago)
- Decision due
- 3 Dec 2014 · decided 18 Nov 2014
- Decision
- Conditional on 18 Nov 2014
- Proposed development
- Construction of two plant rooms for operating the storm gates permitted by planning permission ref. 12/00651. One of the plant rooms will be located on Duffy's Pier, the other at the outer end of the breakwater pier will be the main control room for the operation of the storm gatesAs published by the register.
- Site area
- 23 m² from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 18 · 500 m · 5 years
- GrantedAonad 1, Páirc Ghnó Údarás na Gaeltachta, Baile Iarthach Thuaidh, Oileán Chléire, Co. Chorcaí
- WithdrawnAonad 1, Pairc Ghno Udaras na Gaeltachta, Baile Iarthach Thuaidh, Oilean Chleire, Co. Chorcai
- CommencedBaile Iarthach Thuaidh Oileán Cléire Co. Chorcaí
- CommencedCnocán an Choimhthigh Oileán Chléire Co. Chorcaí
- CommencedCnocán an Choimhthigh Oileán Chléire Co. Chorcaí
- WithdrawnCnocán an Choimhthigh Oileán Chléire Co Chorcaí
- CommencedPáirc Ghnó Údarás na Gaeltachta Baile Iarthach Thuaidh Oileán Chléire An Sciobairín
- CommencedBallyieragh North Cape Clear Island Co. Cork
Show all 18
- CommencedPáirc Ghnó Údarás na Gaeltachta Baile Iarthach Thuaidh Oileán Chleire An Sciobairín, Contae Chorcaí
- CommencedPáirc Ghnó Údarás na Gaeltachta Baile an Iarthach Thuaidh Oileán Chléire, An Sciobairín
- CommencedPáirc Ghnó Údarás na Gaeltachta Baile Iarthach Thuaidh Oileán Chléire An Sciobairín
- CommencedPáirc Ghnó Údarás na Gaeltachta Baile Iarthach Thuaidh Oileán Chléire, An Sciobairin
- CommencedPáirc Ghnó Údarás Baile Iarthach Thuaidh Oileán Chléire An Sciobairín
- CommencedPáirc Ghnó Údarás na Gaeltachta Baile Iarthach Thuaidh Oileán Chléire An Sciobairín
- CommencedPáirc Ghnó Údarás na Gaeltachta Baile Iarthach Thuaidh Oileán Chléire An Sciobairín Co. Chorcaí
- CommencedBaile Iarthach Thuaidh Oileán Cléire Co. Chorcaí
- CommencedPairc Ghno Udaras na Gaeltachta Baile Iarthach Thuaidh Oilean Chleire An Sciobairin
- CommencedDuffy's Pier North Harbour Cape Clear Island Skibbereen, Co. Cork
Building started
- 30 Sept 2015 · Builder told the council work was starting CN0010806LL
- 2 Jan 2015 · Builder told the council work was starting CN0004482GC
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
- Recorded monument · 7
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
14/582 is a planning application to Cork County Council for construction of two plant rooms for operating the storm gates permitted by planning, received on 9 Oct 2014; permission was granted with conditions on 18 Nov 2014.