PlanningRegister.ie
Cork County Council · 17/4368

Wallingstown Little Island Co.Cork

Approved in 2017. Approval ran out in 2022.

  1. 20 Feb 2017Received
  2. 13 Apr 2017Conditional
  3. 19 May 2017Final approval
  4. 19 May 2022Approval ran out
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Conditional · 13 Apr 2017
Council
Cork County Council
Type
PERMISSION
Site
299 m²

Live near Wallingstown Little Island Co.Cork?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

The construction of an extension to existing sprinkler pumphouse consisting of a steel frame building with external insulated wall cladding and associated work

Planning details

Reference
17/4368
Local authority
Cork County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
20 Feb 2017
Observations close
27 Mar 2017 (closed 3480 days ago)
Decision due
18 Apr 2017 · decided 13 Apr 2017
Decision
Conditional on 13 Apr 2017
Proposed development
The construction of an extension to existing sprinkler pumphouse consisting of a steel frame building with external insulated wall cladding and associated work
As published by the register.
Site area
299 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 32 · 500 m · 5 years

Show all 32

Explore this area on the map →

Homes nearby

Zoning

C6 — Waterfront

Zoned for waterfront and harbour-related development.

Protections nearby 250 m

No mapped flood area nearby.

  • Recorded monument · 3
    Water mill - horizontal-wheeled; R112468

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

17/4368 is a planning application to Cork County Council for the construction of an extension to existing sprinkler pumphouse consisting of a steel, received on 20 Feb 2017; permission was granted with conditions on 13 Apr 2017.