  1. 22 Jul 2020Received
  2. 11 Sept 2020Unconditional

Earlier approval here ran out with no sign of building: 15/4926 (2015)

Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Unconditional · 11 Sept 2020
Council
Cork County Council
Type
EXTENSION OF DURATION
Site
2.01 ha

Live near Inchera Little Island Co. Cork?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Construction of a renewable bioenergy plant to generate up to 4MW of electricity from 90,000 tonnes of non-hazardous biodegradable waste per annum utilising anaerobic digestion (AD) technology on a 2.01 hectares site. The proposed plant will comprise the following elements: (1) Demolition of the existing decommissioned waste water treatment plant and associated ancillary buildings and the existing utility building located on the east side of the site (c.1425sqm footprint); (2) Main processing building (c.4500sqm floor area up to 14.5m high) incorporating feedstock reception and processing areas, digestate treatment areas, dewatering and storage areas, quarantine areas and the odour control system (c. 12m high, 773sqm floor area) and 25m high stack; (3) Service yard area including 2no. weighbridges, weighbridge office (c.435m high and 17sqm floor area), 2no. car parking spaces, bunded vehicle refuelling area (c.56sqm floor area) with diesel storage tank (2500 litres), workshop (c. 7m high and c. 70sqm floor area), and 1no. wheel wash; (4) Tank farm (c.2900sqm footprint) encompassing 4no. digester tanks (up to 25.5m max. height, c. 5000 metres cubed), 4no. grit removal buffer tanks (up to 24m max. height, c. 630 metres cubed), 2no. post-digestion buffer tanks (up to 24m max. height, c. 630 metres cubed) and 2no. pasteurisation tanks (up to 19m max. height, c. 217metres cubed), 2no. post pasteurisation and sludge storage tanks (up to 24m max. height, c. 630 metres cubed), 1no. process water tank (up to 25.5m max. height, c. 1280 metres cubed), 1no. concentrate tank (up to 10m max. height, c. 240 metres cubed) , 4no. chemical storage tanks (up to 5m max. height, c. 48.1 metres cubed), total 20no. tanks in the tank farm, to include a stairwell tower (up to 25m max. height), gantry walkways, 3m high bund wall, 2no. bund access stairs, and 6no. tank emergency access ladders; (5) 2no. enclosed Combined Heat and Power (CHP) 2MW engines (c. 3.6m high and c.66sqm floor area each), 28m high CHP stack, c.14m high gas storage dome (1800 metres cubed) with 4no. lightning rod electrodes (c.18m high), 8.2m high biogas flare stack, gas treatment equipment enclosed in a c.1.8m high container (c.31sqm floor area) containing a gas booster and dryer and a c.2.5m high container (c.79sqm floor area) containing a boiler, 10m high boiler stack, 3no. bunded electrical transformers (c.5m high with 1m high bund wall and c.117sqm floor area), c.3.0m high substation (c.70sqm flo

Planning details

Reference
20/5549
Local authority
Cork County Council
Status
Granted · register status “APPLICATION FINALISED”
Received
22 Jul 2020
Observations close
26 Aug 2020 (closed 2238 days ago)
Decision due
15 Sept 2020 · decided 11 Sept 2020
Decision
Unconditional on 11 Sept 2020
Proposed development
Construction of a renewable bioenergy plant to generate up to 4MW of electricity from 90,000 tonnes of non-hazardous biodegradable waste per annum utilising anaerobic digestion (AD) technology on a 2.01 hectares site. The proposed plant will comprise the following elements: (1) Demolition of the existing decommissioned waste water treatment plant and associated ancillary buildings and the existing utility building located on the east side of the site (c.1425sqm footprint); (2) Main processing building (c.4500sqm floor area up to 14.5m high) incorporating feedstock reception and processing areas, digestate treatment areas, dewatering and storage areas, quarantine areas and the odour control system (c. 12m high, 773sqm floor area) and 25m high stack; (3) Service yard area including 2no. weighbridges, weighbridge office (c.435m high and 17sqm floor area), 2no. car parking spaces, bunded vehicle refuelling area (c.56sqm floor area) with diesel storage tank (2500 litres), workshop (c. 7m high and c. 70sqm floor area), and 1no. wheel wash; (4) Tank farm (c.2900sqm footprint) encompassing 4no. digester tanks (up to 25.5m max. height, c. 5000 metres cubed), 4no. grit removal buffer tanks (up to 24m max. height, c. 630 metres cubed), 2no. post-digestion buffer tanks (up to 24m max. height, c. 630 metres cubed) and 2no. pasteurisation tanks (up to 19m max. height, c. 217metres cubed), 2no. post pasteurisation and sludge storage tanks (up to 24m max. height, c. 630 metres cubed), 1no. process water tank (up to 25.5m max. height, c. 1280 metres cubed), 1no. concentrate tank (up to 10m max. height, c. 240 metres cubed) , 4no. chemical storage tanks (up to 5m max. height, c. 48.1 metres cubed), total 20no. tanks in the tank farm, to include a stairwell tower (up to 25m max. height), gantry walkways, 3m high bund wall, 2no. bund access stairs, and 6no. tank emergency access ladders; (5) 2no. enclosed Combined Heat and Power (CHP) 2MW engines (c. 3.6m high and c.66sqm floor area each), 28m high CHP stack, c.14m high gas storage dome (1800 metres cubed) with 4no. lightning rod electrodes (c.18m high), 8.2m high biogas flare stack, gas treatment equipment enclosed in a c.1.8m high container (c.31sqm floor area) containing a gas booster and dryer and a c.2.5m high container (c.79sqm floor area) containing a boiler, 10m high boiler stack, 3no. bunded electrical transformers (c.5m high with 1m high bund wall and c.117sqm floor area), c.3.0m high substation (c.70sqm flo
As published by the register.
Site area
2.01 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 16 · 500 m · 5 years

Show all 16

Explore this area on the map →

Homes nearby

Zoning

C6 — Waterfront

Zoned for waterfront and harbour-related development.

Protections nearby 250 m

No mapped flood area nearby.

Nothing else protected nearby.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

20/5549 is a planning application to Cork County Council for construction of a renewable bioenergy plant to generate up to 4MW of electricity from, received on 22 Jul 2020; permission was granted on 11 Sept 2020.