Aughinida Coachford Co. Cork
Approved in Sept 2023. No sign of building yet.
Start notices are matched from the national building control register; a start on site can be missed.
- 24 Mar 2023Received
- 10 Aug 2023Conditional
- 15 Sept 2023Final approval
- 15 Sept 2033Approval runs out
Planning details
- Status
- Approved
- Decision
- Conditional · 10 Aug 2023
- Reference
- 23/4541
- Received
- 24 Mar 2023
- Site
- 4.72 ha
What’s proposed
10 year Planning Permission for a Grid Stability Service Development including the provision of a synchronous condenser enclosed within a building up to 12.5 metres in height with associated plant and apparatus, transformers, circuit breakers, modular electrical control containers, air compressor, cooling equipment, underground cabling (including 110kV connection to the nearby Clashavoon substation), lightning…
Show all
protection masts, perimeter security fencing, drainage infrastructure, landscaping, temporary construction compound, access tracks (new and upgrade of existing), upgrade of existing entrance off the L7477 local road and all ancillary site development works
3 other applications within 500 m in five years
Open the reportNearby 3 · 500 m · 5 years
Protections nearby 250 m
- Recorded monument · 4
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
23/4541 is a planning application to Cork County Council for 10 year Planning Permission for a Grid Stability Service Development including the, received on 24 Mar 2023; permission was granted with conditions on 10 Aug 2023.