Kilmore Brinny Co Cork
Declared invalid.
- 7 Oct 2024Received
- 11 Nov 2024Observations closed
- 2 Dec 2024Decision due
- Status
- Withdrawn or invalid
- Decision
- Due 2 Dec 2024
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 21.89 ha
Live near Kilmore Brinny Co Cork?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
1) Permission for retention and continued use of the existing processing plant and related water management system, the existing concrete plant and ancillary buildings, site access and all related ancillary works/facilities (wheel wash, bunded fuel storage with hydrocarbon interceptor, weighbridge, etc.) permitted under Pl.Reg.No. S/02/1023), all for a duration of 10 years. 2) Permission for proposed development comprising recycling of c. 15,000 tonnes of concrete for use in concrete production, importation of 25,000 tonnes of sand & gravel for processing, importation of c. up to 20,000 tonnes of soil and stone per year (under Article 27) for phased site restoration with a revised phasing plan, and completion of restoration of the overall site to agricultural use. Permission is sought for eight years plus two years for final restoration, total of 10 years. All within an application area of c. 21.4 hectares
Planning details
- Reference
- 24/5882
- Local authority
- Cork County Council
- Status
- Withdrawn or invalid · register status “INCOMPLETED APPLICATION”
- Received
- 7 Oct 2024
- Observations close
- 11 Nov 2024 (closed 699 days ago)
- Decision due
- 2 Dec 2024
- Decision
- Not decided
- Proposed development
- 1) Permission for retention and continued use of the existing processing plant and related water management system, the existing concrete plant and ancillary buildings, site access and all related ancillary works/facilities (wheel wash, bunded fuel storage with hydrocarbon interceptor, weighbridge, etc.) permitted under Pl.Reg.No. S/02/1023), all for a duration of 10 years. 2) Permission for proposed development comprising recycling of c. 15,000 tonnes of concrete for use in concrete production, importation of 25,000 tonnes of sand & gravel for processing, importation of c. up to 20,000 tonnes of soil and stone per year (under Article 27) for phased site restoration with a revised phasing plan, and completion of restoration of the overall site to agricultural use. Permission is sought for eight years plus two years for final restoration, total of 10 years. All within an application area of c. 21.4 hectaresAs published by the register.
- Site area
- 21.89 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 14 · 500 m · 5 years
- WithdrawnKilmore, Brinny, Innishannon, Co. Cork.
- WithdrawnBrinny, Innishannon, Co.Cork
- AppealedKilmore, Brinny, Co. Cork
- GrantedBrinny, Innishannon, Co. Cork.
- GrantedKilmore Brinny Co Cork
- WithdrawnKilmore Brinny Co Cork
- GrantedA site of c. 8.75 ha located at lands Brinny Innishannon Co.Cork
- GrantedKilmore Brinny Co Cork
Show all 14
Homes nearby
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
- NIAH-recorded building · 2
- Recorded monument · 6
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
24/5882 is a planning application to Cork County Council for 1) Permission for retention and continued use of the existing processing plant and, received on 7 Oct 2024; the file is recorded as incompleted application.