Approved in 2020. Building started in 2022.

  1. 8 May 2020Received
  2. 9 Jul 2020Approved
  3. 31 Jul 2020Appealed
  4. 1 Dec 2020Appeal: Approved with conditions
  5. 1 Dec 2020Final approval
  6. 27 Jul 2022Building started
Status
Building startedi
Decision
Approved · 9 Jul 2020
Council
Dublin City Council
Type
Permission
Site
594 m²
Appeal
ACP 307770 · Approved with conditions

Live near No. 74A & 74B Rathgar Road?

Everything else planned on your street, in one report.

Check my street

What’s proposed

The development will consist of, • Change of use of existing structure from commercial use to residential use. • Alterations to the existing structure including demolition of part of the existing single and two storey structure and removal of the existing roof structures. • Construction of part single storey/part two storey residential scheme to include 2 no. 2 bed units and 2 no. 1 bed units. Each residential unit will be provided with rooflights, photovoltaic panels and private outdoor open space at ground and first floor levels. • New entrances to each residential unit from Garville Mews. • All associated internal and external alterations, bin storage and bicycle parking area; landscaping; drainage and all ancillary works necessary to facilitate the development

Planning details

Reference
2679/20
Local authority
Dublin City Council
Status
Commenced · register status “Appeal Decided”
Received
8 May 2020
Observations close
12 Jun 2020 (closed 2309 days ago)
Decision due
17 Jul 2020 · decided 9 Jul 2020
Decision
Grant permission on 9 Jul 2020
Proposed development
The development will consist of, • Change of use of existing structure from commercial use to residential use. • Alterations to the existing structure including demolition of part of the existing single and two storey structure and removal of the existing roof structures. • Construction of part single storey/part two storey residential scheme to include 2 no. 2 bed units and 2 no. 1 bed units. Each residential unit will be provided with rooflights, photovoltaic panels and private outdoor open space at ground and first floor levels. • New entrances to each residential unit from Garville Mews. • All associated internal and external alterations, bin storage and bicycle parking area; landscaping; drainage and all ancillary works necessary to facilitate the development
As published by the register.
Site area
594 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name

Nearby 202 · 500 m · 5 years

Show all 202

Explore this area on the map →

Homes nearby

Development land nearby

From Buildable, our sister site for development land in Dublin.

See all development land near here →

Appeal

ACP 307770 · Planning Appeal · decided · Approved with conditions 1 Dec 2020
received by the Commission 31 Jul 2020 · inspector's report · board order

Building started

  • 25 Jun 2025 · Builder told the council work was starting CN0130102DC
  • 22 Apr 2024 · Builder told the council work was starting CN0113344DC
  • 22 Jun 2023 · Builder told the council work was starting CN0102004DC
  • 1 Feb 2023 · Builder told the council work was starting CN0097281DC
  • 27 Jul 2022 · Builder told the council work was starting CN0092016DC

Zoning

Zone Z1 - DEV PLAN 2022-2028

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

No mapped flood area nearby.

  • Radon risk area · 1
    About 1 in 20 homes in this area is likely to have high radon levels

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: npad · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
npadCC-BY-4.011 Sept 2026, 18:51open
Summary

2679/20 is a planning application to Dublin City Council for the development will consist of, • Change of use of existing structure from commercial, received on 8 May 2020; permission was granted on 9 Jul 2020.