PlanningRegister.ie
Dublin City Council · 3176/23

Block B, George's Quay, Dublin 2, D02 VR98

Approved in May 2023. Built and signed off.

  1. 16 Jan 2023Building started
  2. 7 Feb 2023Received
  3. 3 Apr 2023Approved
  4. 15 May 2023Final approval
  5. 6 Aug 2024Signed off
Status
Building started
Decision
Approved · 3 Apr 2023
Council
Dublin City Council
Type
Permission
Site
1,544 m²

What’s proposed

Permission for amendments to permitted development Reg. Ref. 2532/20 on a site of 0.1483ha. at Block B, George's Quay, Dublin 2, D02 VR98. The site is bound by George's Quay to the north, George's Quay Plaza to the south, 1GQ to the east and Tara Street Station / Railway bridge to the west. Luke Street runs through the site in a north / south direction with the existing building bridging across Luke Street from 1st floor level. The proposed development comprises of the following: (i) provision of an external roof terrace to the north and east elevations with glass balustrade and accompanying stairs and lift; (ii) reduction of stone parapet height at 5th floor level and introduction of glass balustrade; (iii) removal of mezzanine floor at ground floor level, including associated stairs to provide for a double height space; (iv) demolition of the existing portico located between the subject building and 1GQ to the east; (v) enlarged emergency exit door at ground floor level on eastern facade of ground floor west; (vi) provision of additional door and service hatch at ground floor level on the western facade; (vii) relocation of door at ground floor level on eastern facade; (viii) relocation of PV panels and adjustments to plant at roof level; (ix) provision of 2 no. antennas at roof level; (x) adjustment to plant screen to enclose extended stair/lift core at roof level; (xi) increase in the height of the glazed guarding of the 6th floor terrace; (xii) internal core revisions; (xiii) all associated site development works. The proposed development will result in a reduction in gross floor area from 7,791 sq.m. to 7,683 sq.m

Planning details

Reference
3176/23
Local authority
Dublin City Council
Status
Commenced · register status “Decision Notice Issued”
Received
7 Feb 2023
Decision due
3 Apr 2023 · decided 3 Apr 2023
Decision
Grant permission on 3 Apr 2023
Site area
1,544 m² from the mapped boundary, not the council's figure

Live near Block B?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 59 · 500 m · 12 months

Distance
Time
Show all 59

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Building started

  • 6 Oct 2025 · Builder told the council work was starting (seven-day notice) SN0013166DC
  • 1 Nov 2024 · Builder told the council work was starting CN0121610DC
  • 31 Oct 2024 · Builder told the council small works were starting CN0121439DC
  • 3 Jul 2024 · Builder told the council work was starting CN0116765DC
  • 31 May 2024 · Builder told the council work was starting CN0115661DC
  • 20 May 2024 · Builder told the council small works were starting CN0114989DC
  • 8 May 2024 · Builder told the council work was starting CN0114752DC
  • 16 Jan 2023 · Builder told the council work was starting CN0096856DC

Zoning

Zone Z5 - DEV PLAN 2022-2028

M2 — Major town centre

The main town centre — retail, offices, civic uses, apartments.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

  • NIAH-recorded building · 75
    'Famine'; Custom House
  • Recorded monument · 18
    Hospital; Boundary stone

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

3176/23 is a planning application to Dublin City Council for permission for amendments to permitted development Reg. Ref. 2532/20 on a site of, received on 7 Feb 2023; permission was granted on 3 Apr 2023.