25-28 North Wall Quay, Dublin 1, D01 H104
Approved in Jul 2024. Built and signed off.
- 8 Apr 2024Received
- 31 May 2024Approved
- 10 Jul 2024Building started
- 16 Jul 2024Final approval
- 3 Jun 2025Signed off
- Status
- Building started
- Decision
- Approved · 31 May 2024
- Council
- Dublin City Council
- Type
- Permission
- Site
- 4,673 m²
What’s proposed
PERMISSION & RETENTION PERMISSION for development at the A&L Goodbody Building, 25-28 North Wall Quay, Dublin 1, DO1 H104. The site is bound by North Wall Quay to the south, an access ramp to existing basement to the east, Alderman Way to the north and the Spencer Hotel/an unnamed laneway to the west. The proposed development consists of the following amendments to the external elevations, internal layout and roof layout of the permitted building under Reg. Ref.: 3245/20 (as amended by Reg. Ref.: 4202/21) which is currently under construction: Planning permission is sought for: 1. Change in materiality to the southern stair cores. 2. Alterations to the main entrance to improve universal access. 3. Changes to the number and location of external doors. 4. Addition of a security gate to the basement car park. 5. Amendments to the reception and main core layouts. 6. Alterations to the landscaping to the south of the building. 7. Amendments to the landscaping to the north, east and west to allow for ESB access requirements (resulting in the loss of 1 no. car parking space) 8. Provision of a lightwell to the basement area. 9. Changes at basement level to provide additional space for Active commuter Facilities. 10. Reconfiguration of the basement layout resulting in a reduction from 64 no. to 58 no. car parking spaces and 8 no. to 3 no. motorcycle spaces. 11. Changes to layout of bicycle parking with no change to number of spaces. 12. Alterations to landscaping at level 6 and level 7. 13. Amendments at roof level including height of plan screen, extent of plant enclosure, increase in extent of proposed atrium roof and PV panels location. 14. Omit plant space in lieu of roof lights at level 1 roof. 15. Alterations to the level 6 south building permitted signage. 16. Change in location of permitted signage at main entrance. 17. New high level building signage to northeast core. Retention and completion permission is sought for: 1. Minor alterations to the FFLs of levels 1-7. 2. Change in modulation of channels to the main south elevation levels 2-5. 3. Change in materiality of spandrel panels to the north, east and west elevations. 4. Change in extent and materiality to northern stair cores. 5. Change to ground & 1st floor elevation to the west of the main entrance. 6. Alterations to the shape of the atrium and location of the feature stairs. 7. Addition of a roof access stairs. The above works result in an increase in GFA by 194 sq.m (125 sq.m proposed (planning permission) 69 sq.m to be retained (retention permission)) from 18,131 sq.m. (excluding basement of 3,708 sq.m.) to 18,325 sq.m. (excluding basement of 3,670 sq.m.)
Planning details
- Reference
- 3500/24
- Local authority
- Dublin City Council
- Status
- Commenced · register status “Decision Notice Issued”
- Received
- 8 Apr 2024
- Decision due
- 31 May 2024 · decided 31 May 2024
- Decision
- Grant permission on 31 May 2024
- Site area
- 4,673 m² from the mapped boundary, not the council's figure
Live near 25-28 North Wall Quay?
Everything else planned on your street, in one report.
Check my streetNearby 20 · 500 m · 12 months
- Awaiting decisionWaste Energy Facility, Poolbeg Peninsula, Pigeon House Road, Dublin 4, Boiler Station, Park Lane, Spencer Dock, Dublin 2
- Granted9 Magennis Square, Dublin 2, D02NC86
- Withdrawn9 Magennis Square, Dublin 2, Co. Dublin, D02NC86
- Awaiting decision24A First Avenue, North Wall, Dublin 1, D01 E244
- Awaiting decisionCitigroup Building, 1 North Wall Quay, Dublin 1, D01 T8Y1. The site is bound by North Wall Quay to the south, Commons Street to the west, Clarion Quay/Alderman Way to the north and an access ramp to the existing basement to the east. D01 T8Y1
- WithdrawnCitigroup Building, 1 North Wall Quay, Dublin 1, D01 T8Y1 The site is bound by North Wall Quay to the South, Commons Street to the West, Clarion Quay/Alderman Way to the North and an access ramp to the existing basement to the East., D01 T8Y1
- Awaiting decision67 Fourth Avenue, Seville Place, Dublin 1
- Awaiting decision81B Campshires, Sir John Rogerson’s Quay, Dublin 2, D02 NW20
Show all 20
- Withdrawn81B Campshires, Sir John Rogerson’s Quay, Dublin 2, D02 NW20
- Grantedc.1.34 ha site located at the junction of North Wall Quay and New Wapping Street, Salesforce Tower, Station Square, Block 7, Spencer Dock, Dublin 1
- GrantedUnits 9-11, Saunders House, Spencer Dock, Dublin 1, D01 WY95
- Granted1, George's Dock, I.F.S.C., Dublin 1
- Withdrawnc.1.34 ha site located at the junction of North Wall Quay and New Wapping Street, Salesforce Tower, Station Square, Block 7, Spencer Dock, Dublin 1
- GrantedHilton Garden Inn Hotel, Custom House Quay, North Wall, Dublin 1, D01V9X5
- WithdrawnHilton Garden Inn Hotel, Custom House Quay, North Wall, Dublin 1, D01 V9X5
- Grantedc.1.34 ha site located at the junction of North Wall Quay and New Wapping Street, Salesforce Tower, Station Square, Block 7, Spencer Dock, Dublin 1.
- GrantedHilton Garden Inn, Custom House Quay, Dublin 1, D01 V9X5
- AppealedCitiGroup Building, 1 North Wall Quay, Dublin 1, D01T8Y1
- GrantedLands at the corner of North Wall Quay and Spencer Place, Spencer Dock, City Block Block No. 7, Dublin 1
- GrantedRear of 26 Pearse Square fronting onto Hanover Street ., Dublin 2, D02NP92
- CommencedUnit 40 Forbes Street, Grand Canal Dock, Dublin 2, D02 PP49
- WithdrawnUnit 40 Forbes Street, Grand Canal Dock, Dublin 2, D02 PP49
- Granted1 Sir John Rogerson's Quay, Dublin Docklands, Dublin 2
- GrantedSite at Junction of North Wall Quay and New Wapping Street, Salesforce Tower, Station Square, Block 7, Spencer Dock, Dublin 1, D01 W2Y3
- WithdrawnSite at the junction of North Wall Quay and New Wapping Street, Salesforce Tower, Station Square, Block 7, Spencer Dock, Dublin 1
- CommencedThe Shipping Office Building, Block 1, Unit 2 Lime Street, Dublin 2
- WithdrawnThe Shipping Office Building, Block 1, Unit 2, Lime Street, Dublin 2
- Refused24A First Avenue, North Wall, Dublin 1, D01 E244
- CommencedThe Shipping Office, 20-26, Sir John Rogerson's Quay, Dublin 2, D02 Y049
- RefusedHilton Garden Inn, Custom House Quay, North Wall, Dublin 1, D01 V9X5
- Withdrawn24a First Avenue, Northwall, Dublin 1, D01 E244
- WithdrawnThe Shipping Office, 20-26 Sir John Rogerson's Quay, Dublin 2, D02 Y049
- Granted9, Dowling's Court, Dublin 2, D02 CP30
- WithdrawnThe Shipping Office, 20-26, Sir John Rogerson's Quay, Dublin, D02 Y049
- WithdrawnHilton Garden Inn Hotel , Custom House Quay, North Wall, Dublin 1, D01 V9X5
- Withdrawn9, Dowling's Court, Dublin 2, D02 CP30
- CommencedThe Chq Building, (formerly Stack A), Custom House Quay, Dublin 1
- GrantedThe A & L Goodbody, 25North Wall Quay, Dublin 1, D01 H104
- WithdrawnA. & L. Goodbody Building, 25-28, North Wall Quay, Dublin 1, D01 H104
- Granted7-11, Sir John Rogerson's Quay and Windmill Lane, Dublin 2
- Granted50 City Quay & ESB Substation Opposite & North of City Quay, Dublin Docklands, Dublin 2
- Withdrawn50, City Quay, Dublin 2 , D02F588
- GrantedTownhall, 1, Windmill Lane, Dublin 2
- RefusedSouth West Corner of Sheriff Street Upper and Abercorn Road, City Block No. 2, Spencer Dock, Dublin 1
- WithdrawnSouth West Corner of Sheriff Street Upper and Abercorn Road, City Block No. 2, Spencer Dock, Dublin 1
- WithdrawnNorth East Lands of City Block No. 2 Urban Block No. 2A Spencer Dock, Dublin 1
- GrantedUnit 3, Forbes Street, Grand Canal Dock, Dublin 2
- Commenced4-5, Grand Canal Square, Dublin 2
- WithdrawnUnit 3, Forbes Street, Grand Canal Dock, Dublin 2
- GrantedThe Spencer Hotel, Excise Walk, North Wall Quay, Dublin 1
- Granted1, George's Dock, IFSC, Dublin 1, D01 W213
- CommencedKilmore House, Park Lane , Spencer Dock, Dublin 1 , D01 XN99
- GrantedPwC Building, One Spencer Dock, North Wall Quay, Dublin 1, D01X9R7
- CommencedNo's 1-4 Martin's Terrace, Dublin 2 (D02DK03, D02TD56, D02XE14, D02YT10) and adjoining lands, at corner of Macken Street and the new realigned Hanover Street East
- GrantedAnantara, The Marker Dublin Hotel, Grand Canal Square, Dublin 2, D02 CK38
- Commenced7-11, Sir John Rogerson's Quay and Windmill Lane, Dublin 2
- WithdrawnMilano, 6, Excise Walk, Dublin 1
- GrantedPlaza 3, Custom House Plaza, Harbourmaster Place, I.F.S.C., Dublin 1
- WithdrawnMilano, Unit 6, Excise Walk, Dublin 1
- GrantedOn the public footpath at Guild Street, corner of Seville Place, Dublin 1
- WithdrawnOn the public footpath at Guild Street, corner of Seville Place, Dublin 1
- WithdrawnMilano, Unit 6, Excise Walk, Dublin 1
- GrantedSpar, George's Dock, I.F.S.C., Dublin 1
- Appeal decidedCitiGroup Building, 1 North Wall Quay, Dublin 1, D01T8Y1
- Commenced49-51 Third Avenue, Serville Place, Dublin 1, D01 X276
- GrantedBuilding R, Spencer Dock, Mayor Street Upper, Dublin 1
- Withdrawn49-51, Third Avenue, Seville Place, Dublin 1, D01 X276
- WithdrawnBuilding R, Spencer Dock, Mayor Street Upper, Dublin 1
- WithdrawnNo. 26 Pearse Square, Dublin 2, D02 NP92, fronting onto Hanover Street
- Appeal decided10, Pearse Square, Dublin 2, D02 YE09
- CommencedUnit 2 on the corner of Creighton Street and Windmill Lane, Dublin 2
- GrantedThe CHQ Building, North Wall Quay, Dublin 1
- WithdrawnRear of No. 10 Pearse Square, fronting onto Byrne's Lane, Dublin 2, D02 YE09
- CommencedPlaza 2, Custom House Plaza, Harbourmaster Place, I.F.S.C., Dublin 1, D01 V9V4.
- CommencedHilton Garden Inn, Custom House Quay, North Dock, Dublin 1
- WithdrawnRear of No. 10 Pearse Square, fronting onto Byrne's Lane, Dublin 2, D02 YE09
- WithdrawnHilton Garden Inn, Custom House Quay, North Dock, Dublin 1
- Refused123, The Sycamore, Winter Gardens, Pearse Street, Dublin 2
- Commenced24-26 City Quay, Dublin Docklands, Dublin 2, D02 NY19
- GrantedTropical Fruit Warehouse, 30-32 Sir John Rogerson's Quay, Dublin 2, D02 VX90
- GrantedA c. 1.34 ha site located at the junction of North Wall Quay and New Wapping Street, Station Square, Block 7, Spencer Dock, Dublin 1
- CommencedAnantara, The Marker Dublin Hotel, Grand Canal Square, Dublin 2, D02 CK38
- WithdrawnAnantara The Marker Dublin Hotel, Grand Canal Square, Dublin 2, D02 CK38
- Withdrawn123 Winter gardens, Pearse Street, Dublin 2
- CommencedThe Forum, 1 Commons Street, Dublin 1, D01 Y048
- RefusedTropical Fruit Warehouse, 30-32, Sir John Rogerson's Quay, Dublin 2, D02 VX90
- Withdrawn30-32, Tropical Fruit Warehouse, Sir Rogerson's Quay, Dublin 2, D02VX90, a Protected Structure, (RPS. Reference No. 7548) and at the, connected new office building to, the (south) of the Protected, Structure
- CommencedClayton Hotel, No's 3-5 Cardiff Lane, Dublin 2
- WithdrawnClayton Hotel and No's 3-5 Cardiff Lane, Dublin 2
- Commenced50 City Quay, 1-6 Sir John Rogerson's Quay, 21-22 Windmill Lane, 17 Creighton Street, Observatory Building at 7-11 Sir John Rogerson's Quay and Perpetua Fitness, 2 Windmill Lane, Dublin 2
- Commenced10/11 Exchange Place, I.F.S.C., Dublin 1, D01 N4X6
- CommencedThe chq Building (formerly 'Stack A', a Protected Structure, RPS No. 2094), Custom House Quay, Dublin 1
- GrantedA c. 1.34 ha site located at the junction of North Wall Quay and New Wapping Street, Station Square, Block 7, Spencer Dock, Dublin 1.
- Granteda c. 0.0672 ha site at Retail Units A & B, Building R, Spencer Dock, Mayor Street Upper, Dublin 1
- Withdrawn123, Wintergardens, Pearse Street, Dublin 2
- GrantedSite at the rear of Connolly Station, Sheriff Street Lower, Dublin 1, D01 V6V6
- Awaiting decisionUnit 1, Ropemaker Place, Grand Canal Dock, Dublin 2
- RefusedHarbourmaster Pub, Custom House Dock IFSC, Dublin 1 (A Protected Structure), The site is bounded by the Harbourmaster Pub (a Protected S tructure) to the south, George's Dock to the north and east; and an existing road from George's Dock Road to the west.
- WithdrawnUnit 1, Ropemaker Place, Grand Canal Dock, Dublin 2
- GrantedOn the public footpath at the junction of Seville Place, Guild Street And Sheriff Street Upper, Dublin 1
- GrantedThe Sorting Office, Ropemaker Place, Dublin 2, D02 HD23
- Granted1, Commons Street, Dublin 1, D01 Y048
- WithdrawnThe Sorting Office, Ropemaker Place, Dublin 2, D02 HD23
- WithdrawnThe Forum, No. 1, Commons Street, Dublin 1, D01 Y048
- CommencedBuilding R, Spencer Dock, Mayor Street Upper, Dublin 1
- GrantedThe Exchange, I.F.S.C., George's Dock, Dublin 1
- GrantedUnit 2 Gandon House, Custom House Square, Mayor Street Lower, I.F.S.C., Dublin 1
- Commenced14, Magennis Square, Dublin 2
- Withdrawn14, Magennis Square, Dublin 2
- GrantedThe Kiosks at Grand Canal Square, Dublin 2
- WithdrawnSite at Grand Canal Square, Dublin 2
- Granted47-48 Lower Sheriff Street, Dublin 1, D01 TE82 & D01 W8899
- GrantedThe Forum, 1 Commons Street, Dublin 1, D01 YO48
- Withdrawn1 Commons Street, Dublin 1, D01 Y048
- CommencedUnderground Car Park, Block A, Grand Canal Square, Grand Canal Quay, Dublin 2
- GrantedA c. 1.34 ha site located at the junction of North Wall Quay and New Wapping Street, Station Square, Block 7, Spencer Dock, Dublin 1
- WithdrawnUnderground Car Park, Block A, Grand Canal Square, Grand Canal Quay, Dublin 2
- Commenced5-6 Georges Dock, Dublin 1
- GrantedRear of 68 Seville Place, Dublin & adjacent to 1 First Avenue, Dublin 1
- GrantedPark Lane, Spencer Dock, Dublin1
- WithdrawnRear of 68, Seville Place, Dublin 1 & adjacent to 1 First Avenue, Dublin 1
- Commenced1, George's Dock, IFSC, Dublin 1, D01 W213
- Withdrawn1, George's Dock, IFSC, Dublin 1, D01 W213
- CommencedThe Sorting Office, located at Ropemaker Place and Cardiff Lane, Dublin 2, D02 HD23
- AppealedLa Touche House, Custom House Dock, I.f.S.C. Dublin 1
- CommencedSite at the junction of North Wall Quay and New Wapping Street, City Block 7, Spencer Dock, Dublin 1
- GrantedSite generally bounded by North Wall Quay, Castleforbes Road, New Wapping Street and Mayor Street Upper, Dublin 1
- Granted30-32, Sir John Rogerson's Quay, Dublin 2
- WithdrawnSite generally bounded by North Wall Quay, Castleforbes Road, New Wapping Street and Mayor Street Upper, Dublin 1
- Commenced'Dublin Arch', on a site adjacent to Connolly Station, Sheriff Street Lower, Dublin 1, D01 V6V6
- Withdrawn'Dublin Arch', a site adjacent to Connolly Station, Sheriff Street Lower, Dublin 1, D01 V6V6
- WithdrawnSite at La Touche House, Custom House Dock, I.f.s.c., Dublin 1
- GrantedUnits 9-11, Saunders House, Spencer Dock, Dublin 1, D01 WY95
Homes nearby
- For sale1 Block 1 Clarion Quay, Excise Walk, IFSC, Dublin 1, D01 EW98
- For saleApt 6, Block 1, Clarion Quay, Dublin 1, D01 X004
- For sale14 Block 8 Clarion Quay, IFSC, Dublin 1, D01 A344
- For sale7 Block 3 Clarion Quay, IFSC, Dublin 1, D01 TN30
- For saleApartment 14, Block 7, Clarion Quay, Excise Walk, IFSC, Dublin 1, D01 VE83
- For sale1 Lagan House, Custom House Square, Mayor Street Lower, IFSC, Dublin 1, D01 E430
Development land nearby
- Permission running out · 23 homes granted 13 Dec 2021, expires 13 Dec 2026 — 17 Pearse Square (0.5 km)
- Permission running out · 58 homes granted 25 Aug 2022, expires 25 Aug 2027 — Alexander Terrace and Castleforbes Road (0.7 km)
- Permitted, not started · 87 homes granted 28 Feb 2024, expires 28 Feb 2029 — 62-64 Fenian Street and Bass Place (0.7 km)
- Public land off Custom House Harbour, Custom House Quay, Dublin 1 (0.1 km)
- Public land off Shannon House, Dublin 2 (0.1 km)
Building started
- 10 Jul 2024 · Builder told the council work was starting (seven-day notice) SN0010610DC
Zoning
Zone Z5 - DEV PLAN 2022-2028
The main town centre — retail, offices, civic uses, apartments.
Protections nearby 250 m
Flood area nearby (OPW maps). floodinfo.ie ↗
- EPA-licensed facility · 1
- Natural Heritage Area (incl. proposed) · 1
- NIAH-recorded building · 12
- Recorded monument · 2
Where this comes from
National planning feed (NPAD), fetched 11 Sept 2026, 18:51.
Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 11 Sept 2026, 18:51 | open |
Summary
3500/24 is a planning application to Dublin City Council for PERMISSION & RETENTION PERMISSION for development at the A&L Goodbody Building, 25-28, received on 8 Apr 2024; permission was granted on 31 May 2024.