Approved in Sept 2021. Building started in 2022.

  1. 22 Feb 2021Received
  2. 19 May 2021Approved
  3. 14 Jun 2021Appealed
  4. 21 Sept 2021Appeal: Approved with conditions
  5. 21 Sept 2021Final approval
  6. 11 Jul 2022Building started
Status
Building startedi
Decision
Approved · 19 May 2021
Council
Dublin City Council
Type
Permission
Site
459 m²
Appeal
ACP 310503 · Approved with conditions

What’s proposed

To demolish an existing rear single storey utility room, lean to boiler room and the existing rear single storey kitchen extension comprising a combined total of 25 m2 and to erect a new single storey extension to the rear and part (east) side elevation at ground floor to provide a total of 45 m2 of floor area providing a net increase of 20 m2 at ground floor, a new rear first floor extension comprising 14 m2, the removal of a length of 5 m of existing railings to the side elevation to accommodate the new side extension and the raising of the rear east garden wall in part to enable the formation of a new gated entrance to the rear garden to the existing east garden wall at at 2 Cremore Road D11 A6C9 (on the corner with Cremore Park), Glasnevin, Dublin 11

Planning details

Reference
WEB1150/21
Local authority
Dublin City Council
Status
Commenced · register status “Appeal Decided”
Received
22 Feb 2021
Decision due
19 May 2021 · decided 19 May 2021
Decision
Grant permission on 19 May 2021
Site area
459 m² from the mapped boundary, not the council's figure

Live near 2 Cremore Road?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 21 · 500 m · 12 months

Distance
Time
Show all 21

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Appeal

ACP 310503 · Planning Appeal · decided · Approved with conditions 21 Sept 2021
received by the Commission 14 Jun 2021 · inspector's report · board order

Building started

  • 14 Jul 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0130796DC
  • 11 Jul 2022 · Builder told the council work was starting (opted out of the finish sign-off) CN0091095DC

Zoning

Zone Z1 - DEV PLAN 2022-2028

G5 — Open space and amenity

Land zoned to stay open — parks, playing fields, amenity corridors. Built development is very hard to justify, which also means the view is protected.

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

  • NIAH-recorded building · 3
    Aylward House; house
  • Recorded monument · 4
    Enclosure; R149659

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

WEB1150/21 is a planning application to Dublin City Council for to demolish an existing rear single storey utility room, lean to boiler room and the, received on 22 Feb 2021; permission was granted on 19 May 2021.