Upper Illies, Illies Townland, Co. Donegal
Approved in Apr 2025. No sign of building yet.
Start notices are matched from the national building control register; a start on site can be missed.
- 21 Jan 2025Received
- 6 Mar 2025Conditional
- 9 Apr 2025Final approval
- 8 Apr 2050Approval runs out
Planning details
- Status
- Approved
- Decision
- Conditional · 6 Mar 2025
- Reference
- 2560056
- Received
- 21 Jan 2025
- Site
- 6.89 ha
What’s proposed
CONSTRUCTION AND OPERATION OF 2 NO. WIND TURBINES COMPRISING OF A STEEL TOWER, NACELLES, AND COMPOSITE FIBRE ROTOR BLADES WITH A HUB HEIGHT OF UP TO 85 METRES, A ROTOR BLADE DIAMETER OF UP TO 82 METRES, AND THUS A BLADE TIP HEIGHT OF UP TO 126 METRES.
Show all
THE PROPOSED DEVELOPMENT INCLUDES: EXTERNAL WIND TURBINE TRANSFORMERS, TURBINE HARDSTANDS, NEW ACCESS TRACKS, UPGRADING OF EXISTING TRACKS, NEW SITE ENTRANCE, DRAINAGE WORKS INCLUDING DRAINAGE CHANNELS AND SILT TRAPS ALONG THE ACCESS TRACKS, UNDERGROUND ELECTRICAL CABLES, AND ALL ANCILLARY DEVELOPMENT AND ASSOCIATED SITE WORKS
1 other application within 500 m in five years
Get the full reportNearby 1 · 500 m · 5 years
Not held yet for Donegal County Council: zoning.
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2560056 is a planning application to Donegal County Council for construction and operation of 2 no. wind turbines comprising of a steel tower, nacelles, received on 21 Jan 2025; permission was granted with conditions on 6 Mar 2025.