PlanningRegister.ie
Fingal County Council · F20A/0152

22 Bridge Street, Balbriggan, Co. Dublin, K32 FN51

Approved in Aug 2020. The approval ran out in 2025.

  1. 3 Apr 2020Received
  2. 13 Jul 2020Approved
  3. 18 Aug 2020Final approval
  4. 18 Aug 2025Approval ran out
Status
Approved
Decision
Approved · 13 Jul 2020
Council
Fingal County Council
Type
Permission
Site
137 m²

Live near 22 Bridge Street?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Change of use of an existing ground floor commercial and first floor o…

Cut short by the council feed. Full text ↗

Planning details

Reference
F20A/0152
Local authority
Fingal County Council
Status
Granted · register status “Decision made”
Received
3 Apr 2020
Observations close
8 May 2020 (closed 2357 days ago)
Decision due
20 Jul 2020 · decided 13 Jul 2020
Decision
Grant permission on 13 Jul 2020
Site area
137 m² from the mapped boundary, not the council's figure

Nearby 71 · 500 m · 5 years

Show all 71

Explore this area on the map →

Homes nearby

Development land nearby

From Buildable, our sister site for development land in Dublin.

See all development land near here →

Zoning

RD - Road: N/A

M4 — Major town centre

The main town centre — retail, offices, civic uses, apartments.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

  • Architectural Conservation Area · 1
    Balbriggan Historic Town Core ACA
  • NIAH-recorded building · 19
    Balbriggan Railway Station; factory
  • Record of Protected Structures · 27
    Fingal House (Balbriggan Medical Centre); 19th century two-storey corner building

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 15:18.

Source: National Planning Application Database · fetched 11 Sept 2026, 15:18
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 15:18open
Summary

F20A/0152 is a planning application to Fingal County Council for change of use of an existing ground floor commercial and first floor o, received on 3 Apr 2020; permission was granted on 13 Jul 2020.