Fingal County Council · F22A/0314
Wimbletown, Ballyboughal, Co. Dublin
Approved in Jan 2023. Building started in 2023.
- 16 Nov 2022Received
- 12 Dec 2022Approved
- 27 Jan 2023Final approval
- 13 Mar 2023Building started
- Status
- Building startedi
- Decision
- Approved · 12 Dec 2022
- Council
- Fingal County Council
- Type
- Permission
- Site
- 2,142 m²
What’s proposed
New detached two storey house dwelling along with wastewater treatment…
Cut short by the council feed. Full text ↗
Planning details
- Reference
- F22A/0314
- Local authority
- Fingal County Council
- Status
- Commenced · register status “Decision made”
- Received
- 16 Nov 2022
- Decision due
- 13 Dec 2022 · decided 12 Dec 2022
- Decision
- Grant permission on 12 Dec 2022
- Site area
- 2,142 m² from the mapped boundary, not the council's figure
Nearby 1 · 500 m · 12 months
Distance
Time
Homes nearby
Building started
- 13 Mar 2023 · Builder told the council work was starting (opted out of the finish sign-off) CN0098561FL
Zoning
RD - Road: N/A
R3 — Rural cluster
A small rural settlement where only modest infill serving local need is envisaged.
Where this comes from
National planning feed (NPAD), fetched 11 Sept 2026, 15:18.
Source: National Planning Application Database · fetched 11 Sept 2026, 15:18
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 11 Sept 2026, 15:18 | open |
Summary
F22A/0314 is a planning application to Fingal County Council for new detached two storey house dwelling along with wastewater treatment, received on 16 Nov 2022; permission was granted on 12 Dec 2022.