PlanningRegister.ie
Fingal County Council · F22A/0579

Auburn Woods, Malahide

Approved in May 2024. Building started in 2023.

The homes here are sold as Auburn Woods: 28 sold, median €810,573 on the Property Price Register.

This is Auburn House — 69 homes, by Kinwest Limited. Read the scheme page →

  1. 3 Feb 2023Received
  2. 29 Mar 2023Approved
  3. 25 Apr 2023Appealed
  4. 8 Dec 2023Building started
  5. 13 May 2024Appeal: Approved with conditions
  6. 13 May 2024Final approval
Status
Building startedi
Decision
Approved · 29 Mar 2023
Council
Fingal County Council
Type
Permission
Site
8.67 ha
Appeal
ACP 316444 · Approved with conditions

What’s proposed

The preservation and protection of the existing Protected Structure of…

Cut short by the council feed. Full text ↗

Planning details

Reference
F22A/0579
Local authority
Fingal County Council
Status
Commenced · register status “Final Grant”
Received
3 Feb 2023
Decision due
30 Mar 2023 · decided 29 Mar 2023
Decision
Grant permission on 29 Mar 2023
Site area
8.67 ha from the mapped boundary, not the council's figure
Applicant
Kinwest Limited council register

Live near Auburn House?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 9 · 500 m · 12 months

Distance
Time
Show all 9

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Appeal

ACP 316444 · Planning Appeal · decided · Approved with conditions 13 May 2024
received by the Commission 25 Apr 2023 · inspector's report · board order

Building started

  • 30 Sept 2024 · Builder told the council work was starting CN0120442FL
  • 30 Sept 2024 · Builder told the council work was starting (seven-day notice) SN0011290FL
  • 8 Dec 2023 · Builder told the council work was starting CN0108100FL

Zoning

RS - Residential: Ensure that any new development in existing areas would have a minimal impact on and enhance existing residential amenity.

G3 — High amenity

Protected high-amenity landscape. Development is resisted to preserve the character of the area.

G4 — Open space

Open space and recreational amenity, to be preserved as such.

M2 — Major town centre

The main town centre — retail, offices, civic uses, apartments.

M3 — Neighbourhood centre

A local centre: shops, services and apartments over them, serving the surrounding housing.

R1 — New residential

Zoned for new residential communities. This is where large housing schemes are expected to go, subject to the social and physical infrastructure arriving with them.

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

  • Architectural Conservation Area · 1
    Malahide Castle Demesne ACA
  • NIAH-recorded building · 6
    Malahide Castle; milestone/milepost
  • Record of Protected Structures · 3
    Milestone; Auburn House
  • Recorded monument · 5
    Church; Graveyard

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 15:18.

Source: National Planning Application Database · fetched 11 Sept 2026, 15:18
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 15:18open
Summary

F22A/0579 is a planning application to Fingal County Council for the preservation and protection of the existing Protected Structure of, received on 3 Feb 2023; permission was granted on 29 Mar 2023.