Approved in Dec 2021. Building started.

  1. 12 Oct 2021Received
  2. 6 Dec 2021Conditional
  3. 24 Jan 2022Final approval
  4. 20 May 2022Building started
  5. 23 Jan 2027Approval runs out

Planning details

Status
Building started
Decision
Conditional · 6 Dec 2021
Reference
21331
Type
RETENTION
Received
12 Oct 2021
Site
3,495 m²

What’s proposed

Permission for retention and permission for development which will consist of: retaining previous amalgamation of unit 225 first floor, unit 226 at second floor, additional mezzanine floor area and to amalgamate existing 4,105 sq .m retail unit at first and second floor level with existing 1,721 sq.m retail unit at ground floor level including making necessary structural alteration to install escalators and lifts…

Show all

with associated pits, new mall shopfront at ground floor level. altering existing windows and ventilation louvres at ground floor level, erecting new external signage on Merchants Road and Ballalley Lane and all associated works. The proposed development is located adjacent to a segment of the 17th Century Bastion Wall (RPS Ref. 301)

25 other applications within 500 m in the last year · 2 open for comments

Open the free report

Nearby 25 · 500 m · 12 months

Distance
Time
Show all 25

Explore this area on the map →

Homes nearby

Building started

  • 20 May 2022 · Builder told the council work was starting CN0089626GY

Zoning

M2 — Major town centre

The main town centre — retail, offices, civic uses, apartments.

Protections nearby 250 m

  • NIAH-recorded building · 54
    shop/retail outlet; Bank of Ireland
  • Recorded monument · 16
    Graveyard; Bastioned fort
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

21331 is a planning application to Galway City Council for permission for retention and permission for development which will consist of: retaining, received on 12 Oct 2021; permission was granted with conditions on 6 Dec 2021.