PlanningRegister.ie
Galway County Council · 201387

Cloontoa ,

  1. 25 Sept 2020Received
  2. 23 Apr 2021Conditional
  3. 7 Jun 2021Final grant
  4. 6 Jun 2031Permission expires
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Appeal decided — withdrawn
Decision
Conditional · 23 Apr 2021
Council
Galway County Council
Type
PERMISSION
Site
62.22 ha

What’s proposed

For a 10 year planning permission for the construction of a solar PV farm and ancillary infrastructure at Cloontoa, Rinkippeen, Cloonascragh, Barnacurragh and Ballykeaghra, Tuam, Co Galway. The development will consist of approximately 62.6 hectares solar farm comprising photovoltaic panels on ground mounted frames, 20 no. single storey MV substations, 3 no. single storey customer substations, boundary security fencing, 1 no. communications pole, CCTV, associated electricity cabling and ducting, provision of access tracks, access gates and all associated ancillary development and landscaping works, and will have an operational lifespan of 30 years. A Natura Impact Statement will be submitted to the Planning Authority with the application. Gross floor space of proposed works: 673.2 sqm

201387 is a planning application to Galway County Council for for a 10 year planning permission for the construction of a solar PV farm and ancillary, received on 25 Sept 2020; permission was granted with conditions on 23 Apr 2021.

Planning details

Reference
201387
Local authority
Galway County Council
Status
Appeal decided — withdrawn · register status “APPLICATION FINALISED
Received
25 Sept 2020
Observations close
30 Oct 2020 (closed 2150 days ago)
Decision due
26 Apr 2021 · decided 23 Apr 2021
Decision
Conditional on 23 Apr 2021
Proposed development
For a 10 year planning permission for the construction of a solar PV farm and ancillary infrastructure at Cloontoa, Rinkippeen, Cloonascragh, Barnacurragh and Ballykeaghra, Tuam, Co Galway. The development will consist of approximately 62.6 hectares solar farm comprising photovoltaic panels on ground mounted frames, 20 no. single storey MV substations, 3 no. single storey customer substations, boundary security fencing, 1 no. communications pole, CCTV, associated electricity cabling and ducting, provision of access tracks, access gates and all associated ancillary development and landscaping works, and will have an operational lifespan of 30 years. A Natura Impact Statement will be submitted to the Planning Authority with the application. Gross floor space of proposed works: 673.2 sqm
As published by the register.
Site area
62.22 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 4 applications within 500 m in the last 5 years

Explore this area on the map →

Appeal

The register records appeal ABP-310226-21 (status unknown) but we have not matched the ACP case yet.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    No other designation nearby.

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 357464). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/GalwayCC/AppFileRefDetails/201387/0.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open