Approved in Apr 2023. Building started in 2024.

  1. 30 Sept 2022Received
  2. 27 Jan 2023Conditional
  3. 13 Apr 2023Final approval
  4. 25 May 2024Building started
Status
Building startedi
Decision
Conditional · 27 Jan 2023
Council
Kildare County Council
Type
PERMISSION
Site
5,098 m²

What’s proposed

for the construction of a dormer roof extension on existing partially constructed bungalow permitted under planning reference 01/2097, construction of single storey front, side and rear extensions, amendment of existing window opes and existing internal walls. Completion of existing single storey domestic garage (which is currently at sub-floor stage), installation of secondary effluent treatment system, utilisation of existing permitted entrance under planning file ref 01/2097 (option A) or utilisation of existing family farm entrance to access house (option B) and all associated site works

Planning details

Reference
221186
Local authority
Kildare County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
30 Sept 2022
Decision due
13 Feb 2023 · decided 27 Jan 2023
Decision
Conditional on 27 Jan 2023
Site area
5,098 m² from the mapped boundary, not the council's figure

Live near Newtown?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 4 · 500 m · 5 years

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 25 May 2024 · Builder told the council work was starting (opted out of the finish sign-off) CN0116072KE

Protections nearby 250 m

  • Recorded monument · 2
    Ringfort - rath; R148097

Where this comes from

National planning feed (NPAD), fetched 3 Nov 2026, 23:01.

Source: National Planning Application Database · fetched 3 Nov 2026, 23:01
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.03 Nov 2026, 23:01open
Summary

221186 is a planning application to Kildare County Council for for the construction of a dormer roof extension on existing partially constructed, received on 30 Sept 2022; permission was granted with conditions on 27 Jan 2023.