How many new homes were built and granted in Kildare in 2026?
Updated 9 October 2026 · register counted 9 Oct 2026
592 new homes were completed in Kildare in the latest quarter the CSO has published (April to June 2026). On the planning register, councils and the Commission have granted 1,384 homes in 12 schemes of 10+ so far in 2026, and 1,051 homes in granted schemes are under way.
Schemes of 10 or more homes lodged in the last 6 years, from the council registers and the Commission. “Under way” means a commencement notice was filed (or, in Dublin, the councils’ 4Dublin pipeline reports work on site). We show planning, not prices: whether a home qualifies for Help to Buy depends on its price and on you.
The facts
- 592 new homes were completed in Kildare in April to June 2026: 418 scheme houses, 132 apartments and 42 one-off homes. CSO, New Dwelling Completions Q2 2026 (30 July 2026), Table 3
- 8,823 new homes were completed in Ireland in April to June 2026, 3.6% fewer than a year earlier (9,152). CSO, New Dwelling Completions Q2 2026 (30 July 2026), Table 3
- Apartments fell most: 2,658 completed, down 12.2%. Scheme houses rose 2.0% to 4,738. CSO, New Dwelling Completions Q2 2026 (30 July 2026), Table 3
Every council
What to expect
Scheduled The CSO publishes Q3 2026 completions next. Last year's Q3 release came out on 23 October, so expect it in late October; this page updates the day it does. CSO release calendar.
Is a scheme planned next to you? The free planning report for your address lists every application around it, what was decided and what is open for comment now.
Check an address, then get the free report →The detail
Biggest schemes granted or under way in Kildare
- Granted581 homes · Lands at Railpark Maynooth Co. Kildare , Maynooth , ACP Ref: 312671-22…
- Granted309 homes · Ballymany , Newbridge , Co.Kildare
- Granted243 homes · “Harpur Lane” (Leixlip Gate) , in the townlands of Kilmacredock Upper and…
- Under way237 homes · Leixlip Demesne , Leixlip , Co. Kildare
- Granted219 homes · former Devoy Barracks , John Devoy Road , Naas
- Granted213 homes · Site at lands west of Naas Racecourse south of Dublin Road , north of Tipper…
- Granted195 homes · Parson Street , Maynooth , Co. Kildare
- Granted192 homes · Millicent Road , Clane
- Granted172 homes · Devoy Quarter , Naas West , Naas
- Under way167 homes · Southgreen Road & Old Road , Kildare Town , Co. Kildare
- Granted155 homes · Westfield , Green Lane , Leixlip
- Granted152 homes · New Abbey Road , Nicholastown , Kilcullen
- Granted148 homes · Maynooth , Co. Kildare
- Granted139 homes · Within the townland of Naas West , 'Finlay Park' , Naas
- Granted137 homes · “Leixlip Gate” in the townlands of Kilmacredock Upper and Castletown…
Newest grants in Kildare
- Granted213 homes · Site at lands west of Naas Racecourse south of Dublin Road , north of Tipper…
- Granted11 homes · Mount View , Green Lane , Leixlip
- Granted37 homes · Celbridge Lodge , Tea Lane / Church Road , Celbridge
- Granted136 homes · a site of approx. 6.13 ha at Southgreen Road Kildare Co. Kildare , The site…
- Granted46 homes · Lands at Stonehaven Phase 3 , Tipper West Blessington Road , Naas
- Under way20 homes · Fasagh , Kildangan , Co. Kildare
- Granted95 homes · Site at Boycetown Kilcock Co. Kildare. The application site is located to…
- Granted581 homes · Lands at Railpark Maynooth Co. Kildare , Maynooth , ACP Ref: 312671-22…
Every council
| Council | Completed Q2 (CSO) | Granted 2026 | Under way |
|---|---|---|---|
| Dún Laoghaire-Rathdown | 307 | 1,218 | 3,882 |
| Fingal | 1,020 | 2,732 | 12,116 |
| Dublin City | 1,280 | 1,114 | 6,368 |
| South Dublin | 573 | 4,613 | 10,096 |
| Kildare | 592 | 1,384 | 1,051 |
| Meath | 461 | 2,230 | 2,327 |
| Wicklow | 198 | 535 | 936 |
| Carlow | 99 | 77 | 315 |
| Cavan | 108 | 191 | 379 |
| Clare | 178 | 699 | 592 |
| Cork City | 390 | 18 | 1,462 |
| Cork County | 509 | 1,692 | 1,385 |
| Donegal | 204 | 646 | 350 |
| Galway City | 41 | 375 | 311 |
| Galway County | 237 | 541 | 450 |
| Kerry | 193 | 375 | 223 |
| Kilkenny | 172 | 210 | 530 |
| Laois | 208 | 524 | 667 |
| Leitrim | 32 | 37 | 26 |
| Limerick | 185 | 451 | 675 |
| Longford | 64 | 0 | 30 |
| Louth | 476 | 804 | 1,525 |
| Mayo | 115 | 231 | 139 |
| Monaghan | 92 | 105 | 170 |
| Offaly | 145 | 209 | 418 |
| Roscommon | 74 | 43 | 56 |
| Sligo | 112 | 160 | 285 |
| Tipperary | 169 | 243 | 1,059 |
| Waterford | 151 | 660 | 1,443 |
| Westmeath | 168 | 613 | 665 |
| Wexford | 270 | 595 | 1,293 |
How we counted
- Completed is the CSO’s count of new homes connected to the ESB network (CSO, New Dwelling Completions Q2 2026 (30 July 2026), Table 3), by the council area of the substation. It includes one-off houses.
- Granted in 2026 is from the planning register: schemes of 10 or more homes with a grant (by the council or on appeal) dated this year, one per site. One-off houses and small schemes are left out, so it is not comparable one-for-one with the CSO’s count.
- Under way means a commencement notice is linked to a scheme granted in the last 6 years, or, in Dublin, the 4Dublin Housing Supply Pipeline (CC BY 4.0) reports work on site. 59 of those homes have a commencement notice dated 2026.
- Fingal publishes no unit counts, so some of its schemes may be undercounted. Student and co-living bed spaces are left out.
More: new homes and Help to Buy · named schemes · permitted, not started · new planning applications in Kildare