Leixlip Demesne , Leixlip , Co. Kildare
- 12 May 2023Received
- 4 Aug 2023Conditional
- 18 Dec 2023Final grant
- 17 Dec 2028Permission expires
- Status
- Appeal decided — granted
- Decision
- Conditional · 4 Aug 2023
- Council
- Kildare County Council
- Type
- PERMISSION
- Units
- 237
- Site
- 14.43 ha
What’s proposed
Large-Scale Residential Development (LRD) at a site of c. 14.3 hectares. The application site is principally bounded by: Celbridge Road (R404) and Back Gate Lodge, Celbridge, Leixlip, Co. Kildare W23E0F6 to the west; the existing residential developments of Leixlip Park and Wogansfield to the north; the M4 Motorway to the south; and by agricultural lands to the east. The development will consist of the: (1) Construction of 237 No. residential units ranging in height from two-three storeys comprising 30 no. two-bedroom houses (c.86.8sq.m each), 124 no. three-bedroom houses (ranging in area from c.103sq.m to 114sq.m each), 13 No. four-bedroom houses (ranging from c. 151sq.m to 168sq.m) , 20 No. one-bedroom apartments (ranging in area from c.56.6sq.m each), 22 No. two-bedroom duplex apartments (ranging in area from c. 86.9sq.m to 89.0sq.m) and 22 No. three-bedroom duplex apartments (ranging in area from c.127sq.m to 139sq.m each); (2) Construction of a two storey creche (c.278sq.m in area) with associated external play area (c.85.8sq.m. in area); (3) Provision of public open space (totalling c.7.71 ha of which c.5.61 ha comprises strategic amenity space), communal open space (serving the duplex apartments) (c. 570sq.m), and private open space (in the form of private garden areas serving the houses and terraces/balconies serving the apartments/duplexes); and (4) Provision of vehicular, cyclist and pedestrian access/egress and associated circulation routes (including the construction of a fourth arm to the existing three arm junction on the Celbridge Road (R404) opposite the entrance to the existing Barnhall Meadows residential development and pedestrian and cyclist access to the north-east of the site providing access to the existing residential development known as Leixlip Park). The development will also consist of: (5) 303 No. car parking spaces (including 31 No. car parking spaces for visitors and 12 No. car parking spaces serving the proposed créche): (6) Electric vehicle (EV) charging infrastructure; (7) 355 No. bicycle parking spaces (including 17 No. bicycle parking spaces serving the proposed créche and 160 No. bicycle parking spaces serving the proposed strategic amenity/public open space); (8) Bicycle storage; (9) Bin storage; (10) 3 No. ESB substations; (11) Undergrounding and diversion of the existing 20kV and 38kV overhead power lines; (12) Equipped play areas; (13) Photovoltaic roof panels; (14) Boundary treatments (including gates, piers, ra
23513 is a planning application to Kildare County Council for large-Scale Residential Development (LRD) at a site of c. 14.3 hectares. The application, received on 12 May 2023; permission was granted with conditions on 4 Aug 2023.
Planning details
- Reference
- 23513
- Local authority
- Kildare County Council
- Status
- Appeal decided — granted · register status “APPLICATION FINALISED”
- Received
- 12 May 2023
- Observations close
- 16 Jun 2023 (closed 1187 days ago)
- Decision due
- 8 Aug 2023 · decided 4 Aug 2023
- Decision
- Conditional on 4 Aug 2023
- Proposed development
- Large-Scale Residential Development (LRD) at a site of c. 14.3 hectares. The application site is principally bounded by: Celbridge Road (R404) and Back Gate Lodge, Celbridge, Leixlip, Co. Kildare W23E0F6 to the west; the existing residential developments of Leixlip Park and Wogansfield to the north; the M4 Motorway to the south; and by agricultural lands to the east. The development will consist of the: (1) Construction of 237 No. residential units ranging in height from two-three storeys comprising 30 no. two-bedroom houses (c.86.8sq.m each), 124 no. three-bedroom houses (ranging in area from c.103sq.m to 114sq.m each), 13 No. four-bedroom houses (ranging from c. 151sq.m to 168sq.m) , 20 No. one-bedroom apartments (ranging in area from c.56.6sq.m each), 22 No. two-bedroom duplex apartments (ranging in area from c. 86.9sq.m to 89.0sq.m) and 22 No. three-bedroom duplex apartments (ranging in area from c.127sq.m to 139sq.m each); (2) Construction of a two storey creche (c.278sq.m in area) with associated external play area (c.85.8sq.m. in area); (3) Provision of public open space (totalling c.7.71 ha of which c.5.61 ha comprises strategic amenity space), communal open space (serving the duplex apartments) (c. 570sq.m), and private open space (in the form of private garden areas serving the houses and terraces/balconies serving the apartments/duplexes); and (4) Provision of vehicular, cyclist and pedestrian access/egress and associated circulation routes (including the construction of a fourth arm to the existing three arm junction on the Celbridge Road (R404) opposite the entrance to the existing Barnhall Meadows residential development and pedestrian and cyclist access to the north-east of the site providing access to the existing residential development known as Leixlip Park). The development will also consist of: (5) 303 No. car parking spaces (including 31 No. car parking spaces for visitors and 12 No. car parking spaces serving the proposed créche): (6) Electric vehicle (EV) charging infrastructure; (7) 355 No. bicycle parking spaces (including 17 No. bicycle parking spaces serving the proposed créche and 160 No. bicycle parking spaces serving the proposed strategic amenity/public open space); (8) Bicycle storage; (9) Bin storage; (10) 3 No. ESB substations; (11) Undergrounding and diversion of the existing 20kV and 38kV overhead power lines; (12) Equipped play areas; (13) Photovoltaic roof panels; (14) Boundary treatments (including gates, piers, raAs published by the register.
- Site area
- 14.43 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Full planning report for 53.35954, -6.49941
Zoning, appeals, sold prices, flood and heritage constraints — everything for this area in one PDF.
No account, no payment. Not a statutory planning search.
Appeal
The register records appeal ABP-317923-23 (status unknown) but we have not matched the ACP case yet.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- EPA-licensed facility · 1
- NIAH-recorded building · 10
- Radon risk area · 4
- Recorded monument · 1
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 131548). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/KildareCC/AppFileRefDetails/23513/0.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |