Approved in Dec 2023. No sign of building yet.

  1. 24 Jul 2023Received
  2. 7 Nov 2023Conditional
  3. 18 Dec 2023Final approval
  4. 17 Dec 2028Approval runs out

An email when the builder tells the council work is starting.

Planning details

Status
Approved
Decision
Conditional · 7 Nov 2023
Reference
2360062
Received
24 Jul 2023
Further information
Requested 7 Sept 2023 · received 10 Oct 2023
Site
1,095 m²

What’s proposed

The development will consist of revisions to a permitted 38kV electrical substation and compound previously permitted as part of a solar farm permission by An Bord Pleanála under Ref. ABP-303636-19 (Kildare County Council Planning Ref. 18/250).

Show all

The proposed revisions comprise design alterations to the substation building comprising a modest increase in size and addition of pitched roof; enlargement of compound area with associated revisions to electrical plant and apparatus, security fencing, underground cabling, wastewater holding tank and associated ancillary works

1 other application within 500 m in the last year

Open the report

Nearby 1 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

2360062 is a planning application to Kildare County Council for the development will consist of revisions to a permitted 38kV electrical substation and, received on 24 Jul 2023; permission was granted with conditions on 7 Nov 2023.