Approved in Jul 2024. Building started in 2025, signed off as finished in Jul 2026.

What’s proposed

For change of use to a parish centre (St. Michael’s), alterations to the vehicular entrance, boundary wall and car parking arrangements; internal alterations and layout changes, new access ramp, external signage and the provision of all associated site development works. Revised by Significant Further Information of revisions to the site boundary to exclude the existing tree and ramp, and alterations to the proposed parking layout

  1. 15 Dec 2023Received
  2. 17 Jun 2024Conditional
  3. 29 Jul 2024Final approval
  4. 10 Mar 2025Building started
  5. 21 Jul 2026Signed off

Planning details

Status
Building started
Decision
Conditional · 17 Jun 2024
Reference
2360491
Received
15 Dec 2023
Further information
Requested 15 Feb 2024 · received 26 Apr 2024
Site
2,149 m²

6 other applications within 500 m in the last year

Get the full report

Nearby 6 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 10 Mar 2025 · Builder told the council work was starting CN0126293KE

Zoning

M2 — Major town centre

The main town centre — retail, offices, civic uses, apartments.

S5 — Sustainable neighbourhood infrastructure

Reserved for the schools, creches, community and health facilities a neighbourhood needs.

Protections nearby 250 m

  • NIAH-recorded building · 48
    Saint Michael's Convent; gates/railings/walls
  • Recorded monument · 9
    Historic town; Town defences
Where this comes from

National planning feed (NPAD), fetched 24 Nov 2026, 23:00.

Source: National Planning Application Database · fetched 24 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.024 Nov 2026, 23:00open
Summary

2360491 is a planning application to Kildare County Council for for change of use to a parish centre (St. Michael’s), alterations to the vehicular, received on 15 Dec 2023; permission was granted with conditions on 17 Jun 2024.